Compare / ADARSH PARK HEIGHTS PHASE-2 vs BELVEDERE BY UKN AIRPORT DISTRICT -PHASE 2

ADARSH PARK HEIGHTS PHASE-2 vs BELVEDERE BY UKN AIRPORT DISTRICT -PHASE 2

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
3 complaints · 65% built
AKARSHA REALTY PRIVATE LIMITED PRM/KA/RERA/1251/446/PR/200923/006275
On track · 43% built
U.K.N. PROPERTIES PRIVATE LIMITED PRM/KA/RERA/1251/309/PR/060324/006682
ADARSH PARK HEIGHTS PHASE-2
Construction
65%
as of Q1 2026-27
Sold
458
of 494 · +0 last qtr
Available
36
BELVEDERE BY UKN AIRPORT DISTRICT -PHASE 2
Construction
43%
as of Q1 2026-27
Sold
327
of 595 · +1 last qtr
Available
277
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
ADARSH PARK HEIGHTS PHASE-2
Complaints
3
on this project · 8 on AKARSHA REALTY PRIVATE LIMITED overall
BELVEDERE BY UKN AIRPORT DISTRICT -PHASE 2
Complaints
0
on this project · 1 on U.K.N. PROPERTIES PRIVATE LIMITED overall
Builder track record
Across each promoter's other K-RERA registered projects
ADARSH PARK HEIGHTS PHASE-2
AKARSHA REALTY PRIVATE LIMITED
1 other project on K-RERA · 0 delivered (100% complete) · avg 65.0% complete
BELVEDERE BY UKN AIRPORT DISTRICT -PHASE 2
U.K.N. PROPERTIES PRIVATE LIMITED
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
ADARSH PARK HEIGHTS PHASE-2
No risk signals from filed quarters.
BELVEDERE BY UKN AIRPORT DISTRICT -PHASE 2
No risk signals from filed quarters.
ADARSH PARK HEIGHTS PHASE-2 — escrow account details
Bank
RATNAKAR BANK
Branch
Residency Road, Bangalore
IFSC
RATN0000156
70% Collection A/C
409002464160
100% A/C
409002464146
30% A/C
409002464177
BELVEDERE BY UKN AIRPORT DISTRICT -PHASE 2 — escrow account details
Bank
HDFC
Branch
Kasturba Gandhi Marg
IFSC
HDFC0000009
70% Collection A/C
50200090701289
100% A/C
50200090643758
30% A/C
50200090703588
ADARSH PARK HEIGHTS PHASE-2 — details
Total units
494
Total cost
₹487.10 Cr
Project start
2023-08-01
Proposed completion
2027-05-31
Address
GUNJUR VILLAGE, VARTHUR HOBLI, BANGALORE EAST
BELVEDERE BY UKN AIRPORT DISTRICT -PHASE 2 — details
Total units
595
Total cost
₹332.96 Cr
Project start
2024-03-01
Proposed completion
2031-02-28
Address
Khata No. 799, Sy No. 4, Pattandura Agrahara, K R Puram Hobli, Bangalore East Taluk, Bangalore