Compare / SOBHA Crystal Meadows Phase 1 Wing 1 to 6 vs SOBHA Crystal Meadows Phase 3 Wing 9 to 15

SOBHA Crystal Meadows Phase 1 Wing 1 to 6 vs SOBHA Crystal Meadows Phase 3 Wing 9 to 15

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
0 complaints · 0% built
SOBHA LIMITED PRM/KA/RERA/1251/446/PR/280324/006733
0 complaints · 0% built
SOBHA LIMITED PRM/KA/RERA/1251/446/PR/280324/006735
SOBHA Crystal Meadows Phase 1 Wing 1 to 6
Construction
0%
as of Q4 2025-26
Sold
—
of 66 · +0 last qtr
Available
66
SOBHA Crystal Meadows Phase 3 Wing 9 to 15
Construction
0%
as of Q4 2025-26
Sold
—
of 59 · +0 last qtr
Available
59
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
SOBHA Crystal Meadows Phase 1 Wing 1 to 6
Complaints
0
on this project · 226 on SOBHA LIMITED overall
SOBHA Crystal Meadows Phase 3 Wing 9 to 15
Complaints
0
on this project · 226 on SOBHA LIMITED overall
Builder track record
Across each promoter's other K-RERA registered projects
SOBHA Crystal Meadows Phase 1 Wing 1 to 6
SOBHA LIMITED
37 other projects on K-RERA · 9 delivered (100% complete) · avg 58.0% complete · 59 complaints across those projects
SOBHA Crystal Meadows Phase 3 Wing 9 to 15
SOBHA LIMITED
37 other projects on K-RERA · 9 delivered (100% complete) · avg 58.0% complete · 59 complaints across those projects
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
SOBHA Crystal Meadows Phase 1 Wing 1 to 6
Filing overdue no update in 230 days
Promoter pattern 1 of 36 other projects show the same delay-risk pattern
SOBHA Crystal Meadows Phase 3 Wing 9 to 15
Filing overdue no update in 230 days
Promoter pattern 1 of 36 other projects show the same delay-risk pattern
SOBHA Crystal Meadows Phase 1 Wing 1 to 6 — escrow account details
Bank
Axis Bank
Branch
MG Road, Bangalore
IFSC
UTIB0000009
70% Collection A/C
923020012829774
100% A/C
923020012829891
30% A/C
923020012829877
SOBHA Crystal Meadows Phase 3 Wing 9 to 15 — escrow account details
Bank
Axis Bank
Branch
MG Road, Bangalore
IFSC
UTIB0000009
70% Collection A/C
923020012829815
100% A/C
923020012829909
30% A/C
923020012829877
SOBHA Crystal Meadows Phase 1 Wing 1 to 6 — details
Total units
66
Total cost
₹361.91 Cr
Project start
2024-08-01
Proposed completion
2029-12-31
Address
Balagere, Bangalore
SOBHA Crystal Meadows Phase 3 Wing 9 to 15 — details
Total units
59
Total cost
₹315.57 Cr
Project start
2024-08-01
Proposed completion
2032-12-31
Address
Sy nos - 51/1(P), 51/2(P), 52/1(P), 52/2(P)&53 at Yadavanahalli village, Attibele hobli, Anekal taluk, Bangalore, Karnataka