Compare / SOBHA Crystal Meadows Phase 2 Wing 7 and 8 vs SATTVA SPRINGS

SOBHA Crystal Meadows Phase 2 Wing 7 and 8 vs SATTVA SPRINGS

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
0 complaints · 0% built
SOBHA LIMITED PRM/KA/RERA/1251/446/PR/280324/006734
SATTVA SPRINGS
Bengaluru Urban · Bengaluru North
On track · 42% built
Sattva Resi Private Limited PRM/KA/RERA/1251/310/PR/240724/006948
SOBHA Crystal Meadows Phase 2 Wing 7 and 8
Construction
0%
as of Q4 2025-26
Sold
—
of 59 · +0 last qtr
Available
59
SATTVA SPRINGS
Construction
42%
as of Q2 2026-27
Sold
25
of 66 · +0 last qtr
Available
41
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
SOBHA Crystal Meadows Phase 2 Wing 7 and 8
Complaints
0
on this project · 226 on SOBHA LIMITED overall
SATTVA SPRINGS
Complaints
0
on this project · 2 on Sattva Resi Private Limited overall
Builder track record
Across each promoter's other K-RERA registered projects
SOBHA Crystal Meadows Phase 2 Wing 7 and 8
SOBHA LIMITED
37 other projects on K-RERA · 9 delivered (100% complete) · avg 58.0% complete · 59 complaints across those projects
SATTVA SPRINGS
Sattva Resi Private Limited
8 other projects on K-RERA · 1 delivered (100% complete) · avg 33.7% complete · 2 complaints across those projects
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
SOBHA Crystal Meadows Phase 2 Wing 7 and 8
Filing overdue no update in 230 days
Promoter pattern 1 of 36 other projects show the same delay-risk pattern
SATTVA SPRINGS
Delay risk trending ~27 month(s) past declared completion
Promoter pattern 4 of 6 other projects show the same delay-risk pattern
SOBHA Crystal Meadows Phase 2 Wing 7 and 8 — escrow account details
Bank
Axis Bank
Branch
MG Road, Bangalore
IFSC
UTIB0000009
70% Collection A/C
923020012829828
100% A/C
923020012829884
30% A/C
923020012829877
SATTVA SPRINGS — escrow account details
Bank
FEDERAL BANK OF INDIA
Branch
St. Marks Road Branch, Bangalore
IFSC
FDRL0001104
70% Collection A/C
11040200034133
100% A/C
11040200034224
30% A/C
11040200034158
SOBHA Crystal Meadows Phase 2 Wing 7 and 8 — details
Total units
59
Total cost
₹348.46 Cr
Project start
2024-08-01
Proposed completion
2031-06-30
Address
Balagere, Bangalore
SATTVA SPRINGS — details
Total units
66
Total cost
₹239.65 Cr
Project start
2024-04-01
Proposed completion
2027-09-18
Address
Survey No. 10/3, 11/1, and 11/2, situated at Mallasandra Village, Uttarahalli Hobli, Kanakapura Road, Bengaluru