ANTARES vs ABISH EVARA
Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
ANTARES
Dakshina Kannada · Mangalore
On track · 23% built
CITADEL PROJECTS AND DEVELOPERS PRIVATE LIMITED
PRM/KA/RERA/1257/334/PR/180424/006805
ABISH EVARA
Dakshina Kannada · Mangalore
On track · 3% built
ABISH BUILDERS PRIVATE LIMITED
PRM/KA/RERA/1257/334/PR/240626/008751
ANTARES
Construction
23%
as of Q1 2026-27
Sold
31
of 62
· +3 last qtr
Available
31
ABISH EVARA
Construction
3%
as of Q1 2026-27
Sold
—
of 78
· +0 last qtr
Available
78
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
ANTARES
Complaints
0
on this project
ABISH EVARA
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
ANTARES
CITADEL PROJECTS AND DEVELOPERS PRIVATE LIMITED
No other K-RERA registered projects on file for this promoter.
ABISH EVARA
ABISH BUILDERS PRIVATE LIMITED
1 other project on K-RERA
· 0 delivered (100% complete)
· avg 28.0% complete
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
ANTARES
Delay risk
trending ~51 month(s) past declared completion
ABISH EVARA
No risk signals from filed quarters.
ANTARES — escrow account details
ABISH EVARA — escrow account details
ANTARES — details