Compare / Pursuit of a Radical Rhapsody Tower 5 vs Sobha Infinia Phase 2B Block 4 W1 and Block 3 W2

Pursuit of a Radical Rhapsody Tower 5 vs Sobha Infinia Phase 2B Block 4 W1 and Block 3 W2

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
0 complaints · 28% built
Total Environment Habitat Pvt. Ltd. PRM/KA/RERA/1251/446/PR/281222/005565
0 complaints · 31% built
SOBHA LIMITED PRM/KA/RERA/1251/446/PR/030824/006957
Pursuit of a Radical Rhapsody Tower 5
Construction
28%
as of Q2 2026-27
Sold
108
of 130 · +0 last qtr
Available
22
Sobha Infinia Phase 2B Block 4 W1 and Block 3 W2
Construction
31%
as of Q2 2026-27
Sold
38
of 150 · +4 last qtr
Available
112
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Pursuit of a Radical Rhapsody Tower 5
Complaints
0
on this project · 26 on Total Environment Habitat Pvt. Ltd. overall
Sobha Infinia Phase 2B Block 4 W1 and Block 3 W2
Complaints
0
on this project · 225 on SOBHA LIMITED overall
Builder track record
Across each promoter's other K-RERA registered projects
Pursuit of a Radical Rhapsody Tower 5
Total Environment Habitat Pvt. Ltd.
1 other project on K-RERA · 0 delivered (100% complete) · avg 9.0% complete
Sobha Infinia Phase 2B Block 4 W1 and Block 3 W2
SOBHA LIMITED
37 other projects on K-RERA · 9 delivered (100% complete) · avg 57.1% complete · 59 complaints across those projects
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Pursuit of a Radical Rhapsody Tower 5
Delay risk no completion progress across filed quarters
Escrow 3 quarter(s) withdrawn with no matching progress
Sobha Infinia Phase 2B Block 4 W1 and Block 3 W2
Escrow 2 quarter(s) withdrawn with no matching progress
Promoter pattern 1 of 36 other projects show the same delay-risk pattern
Pursuit of a Radical Rhapsody Tower 5 — escrow account details
Bank
STATE BANK OF INDIA
Branch
COMMERCIAL BRANCH, BANGALORE
IFSC
SBIN0004196
70% Collection A/C
42528977723
100% A/C
42528978524
30% A/C
42528978046
Sobha Infinia Phase 2B Block 4 W1 and Block 3 W2 — escrow account details
Bank
KOTAK MAHINDRA BANK
Branch
Ashok Nagar
IFSC
KKBK0008066
70% Collection A/C
5548931588
100% A/C
5548931601
30% A/C
5548931618
Pursuit of a Radical Rhapsody Tower 5 — details
Total units
130
Total cost
₹459.92 Cr
Project start
2022-12-01
Proposed completion
2029-12-01
Address
SyNo170P1701A1691to1694176317717211722175and1361, HoodiVillageKRPuramHobliWardNo82Bangalore
Sobha Infinia Phase 2B Block 4 W1 and Block 3 W2 — details
Total units
150
Total cost
₹517.44 Cr
Project start
2025-03-01
Proposed completion
2030-12-30
Address
Sy No. 107(P), 115/2, 115/3, 115/4, 115/5, 116/3 situated at Nagondanahalli village and Sy No. 30/1, 30/6, Situated at Hagadur Village, K.R.Puram Hobli