ORIONIS OPAL vs One Life Phase III ,IV & V
Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
ORIONIS OPAL
Belagavi · Belagavi
On track · 42% built
M/s. VARDHAMAN VENTURES
PRM/KA/RERA/1249/447/PR/270226/008492
One Life Phase III ,IV & V
Belagavi · Belagavi
On track · 5% built
Ambica Infra Build
PRM/KA/RERA/1249/447/PR/210126/008416
ORIONIS OPAL
Construction
42%
as of Q1 2026-27
Sold
49
of 100
· +0 last qtr
Available
51
One Life Phase III ,IV & V
Construction
5%
as of Q1 2026-27
Sold
—
of 102
· +0 last qtr
Available
102
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
ORIONIS OPAL
Complaints
0
on this project
One Life Phase III ,IV & V
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
ORIONIS OPAL
M/s. VARDHAMAN VENTURES
1 other project on K-RERA
· 1 delivered (100% complete)
· avg 100.0% complete
One Life Phase III ,IV & V
Ambica Infra Build
1 other project on K-RERA
· 0 delivered (100% complete)
· avg 34.0% complete
ORIONIS OPAL — escrow account details
One Life Phase III ,IV & V — escrow account details
ORIONIS OPAL — details
One Life Phase III ,IV & V — details