MERAKI vs RUDRAM
Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 90% built
MK Infra Holdings Private Limited
PRM/KA/RERA/1268/378/PR/011024/007108
On track · 25% built
Imran Khan
PRM/KA/RERA/1268/378/PR/101225/008324
MERAKI
Construction
90%
as of Q1 2026-27
Sold
21
of 24
· +4 last qtr
Available
3
RUDRAM
Construction
25%
as of Q1 2026-27
Sold
—
of 9
· +0 last qtr
Available
9
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
MERAKI
Complaints
0
on this project
RUDRAM
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
MERAKI
MK Infra Holdings Private Limited
2 other projects on K-RERA
· 0 delivered (100% complete)
· avg 70.0% complete
RUDRAM
Imran Khan
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
MERAKI
No risk signals from filed quarters.
RUDRAM
Delay risk
trending ~8 month(s) past declared completion
MERAKI — escrow account details
RUDRAM — escrow account details
MERAKI — details
RUDRAM — details