Compare / Sobha Sentosa Phase 4 Wing 1 and 2 vs ATMOS TROPICALWOODS

Sobha Sentosa Phase 4 Wing 1 and 2 vs ATMOS TROPICALWOODS

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
7 complaints · 100% built
SOBHA LIMITED PRM/KA/RERA/1251/446/PR/310322/004799
On track · 4% built
ATMOS CONSTRUCTIONS PRIVATE LIMITED PRM/KA/RERA/1251/472/PR/111124/007218
Sobha Sentosa Phase 4 Wing 1 and 2
Construction
100%
as of Q1 2026-27
Sold
141
of 142 · +0 last qtr
Available
1
ATMOS TROPICALWOODS
Construction
4%
as of Q1 2026-27
Sold
38
of 150 · +11 last qtr
Available
112
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Sobha Sentosa Phase 4 Wing 1 and 2
Complaints
7
on this project · 224 on SOBHA LIMITED overall
ATMOS TROPICALWOODS
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
Sobha Sentosa Phase 4 Wing 1 and 2
SOBHA LIMITED
36 other projects on K-RERA · 8 delivered (100% complete) · avg 51.2% complete · 48 complaints across those projects
ATMOS TROPICALWOODS
ATMOS CONSTRUCTIONS PRIVATE LIMITED
1 other project on K-RERA · 0 delivered (100% complete) · avg 39.0% complete
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Sobha Sentosa Phase 4 Wing 1 and 2
Promoter pattern 2 of 35 other projects show the same delay-risk pattern
ATMOS TROPICALWOODS
Escrow 1 quarter(s) withdrawn with no matching progress
Promoter pattern 1 of 1 other projects show the same delay-risk pattern
Sobha Sentosa Phase 4 Wing 1 and 2 — escrow account details
Bank
RATNAKAR BANK
Branch
PRESTIGE TOWERS, ( 0156 ) GROUND FLOOR, G-13, G-14, G-15 AND G-17, PRESTIGE TOWERS, 99, 100 RESIDENCY ROAD, BANGALORE
IFSC
RATN0000156
70% Collection A/C
409002400472
100% A/C
409002400465
30% A/C
409002400489
ATMOS TROPICALWOODS — escrow account details
Bank
HDFC
Branch
Malleshwaram, Bangalore
IFSC
HDFC0000041
70% Collection A/C
57500001735562
100% A/C
57500001735559
30% A/C
57500001734520
Sobha Sentosa Phase 4 Wing 1 and 2 — details
Total units
142
Total cost
₹162.50 Cr
Project start
2023-01-01
Proposed completion
2027-12-31
Address
Balagere, Bangalore
ATMOS TROPICALWOODS — details
Total units
150
Total cost
₹183.74 Cr
Project start
2024-09-02
Proposed completion
2027-09-02
Address
Converted Survey Numbers 103/2, 103/4, 103/6, 103/7, 103/8, 103/9, 104/2, 105/1, 105/2 and 105/7 , Addhevishwanathapura Village, Hesaraghatta Hobli , Yelahanka , Bengaluru Urban, Karnataka - 562157