OVER THE RAINBOW PHASE 1 vs HIVE BY SUMADHURA
Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
OVER THE RAINBOW PHASE 1
Chikkaballapura · Bengaluru East
On track · 16% built
TOTAL ENVIRONMENT PROJECTS (INDIA) PRIVATE LIMITED
PRM/KA/RERA/1254/460/PR/240424/006832
HIVE BY SUMADHURA
Bengaluru Urban · Bengaluru East
On track · 64% built
SUMADHURA INFRACON PRIVATE LIMITED
PRM/KA/RERA/1251/446/PR/051024/007123
OVER THE RAINBOW PHASE 1
Construction
16%
as of Q2 2026-27
Sold
30
of 33
· +2 last qtr
Available
3
HIVE BY SUMADHURA
Construction
64%
as of Q2 2026-27
Sold
5
of 45
· +2 last qtr
Available
40
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
OVER THE RAINBOW PHASE 1
Complaints
0
on this project
HIVE BY SUMADHURA
Complaints
0
on this project · 4 on SUMADHURA INFRACON PRIVATE LIMITED overall
Builder track record
Across each promoter's other K-RERA registered projects
OVER THE RAINBOW PHASE 1
TOTAL ENVIRONMENT PROJECTS (INDIA) PRIVATE LIMITED
No other K-RERA registered projects on file for this promoter.
HIVE BY SUMADHURA
SUMADHURA INFRACON PRIVATE LIMITED
13 other projects on K-RERA
· 1 delivered (100% complete)
· avg 56.4% complete
· 3 complaints across those projects
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
OVER THE RAINBOW PHASE 1
Delay risk
no completion progress across filed quarters
Escrow
2 quarter(s) withdrawn with no matching progress
HIVE BY SUMADHURA
Delay risk
trending ~19 month(s) past declared completion
Promoter pattern
6 of 11 other projects show the same delay-risk pattern
OVER THE RAINBOW PHASE 1 — escrow account details
HIVE BY SUMADHURA — escrow account details
OVER THE RAINBOW PHASE 1 — details
HIVE BY SUMADHURA — details