Compare / SUBHA EDEN-2 vs VRR GOLDEN ENCLAVE PHASE-III

SUBHA EDEN-2 vs VRR GOLDEN ENCLAVE PHASE-III

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 10% built
Subha Luxury Projects LLP PRM/KA/RERA/1251/308/PR/030225/007477
On track · 98% built
H.N.VIJAYARAGHAVA REDDY CO PRM/KA/RERA/1251/308/PR/290425/007698
SUBHA EDEN-2
Construction
10%
as of Q1 2026-27
Sold
1
of 14 · +0 last qtr
Available
13
VRR GOLDEN ENCLAVE PHASE-III
Construction
98%
as of Q1 2026-27
Sold
6
of 13 · +1 last qtr
Available
7
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
SUBHA EDEN-2
Complaints
0
on this project · 2 on Subha Luxury Projects LLP overall
VRR GOLDEN ENCLAVE PHASE-III
Complaints
0
on this project · 1 on H.N.VIJAYARAGHAVA REDDY CO overall
Builder track record
Across each promoter's other K-RERA registered projects
SUBHA EDEN-2
Subha Luxury Projects LLP
1 other project on K-RERA · 0 delivered (100% complete) · avg 7.0% complete
VRR GOLDEN ENCLAVE PHASE-III
H.N.VIJAYARAGHAVA REDDY CO
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
SUBHA EDEN-2
No risk signals from filed quarters.
VRR GOLDEN ENCLAVE PHASE-III
No risk signals from filed quarters.
SUBHA EDEN-2 — escrow account details
Bank
ICICI Bank
Branch
HSR LAYOUT
IFSC
ICIC0003182
70% Collection A/C
318205000873
100% A/C
318205000872
30% A/C
318205000874
VRR GOLDEN ENCLAVE PHASE-III — escrow account details
Bank
Karnataka Bank Ltd.
Branch
KORAMANGALA
IFSC
KARB0000094
70% Collection A/C
0942000100227901
100% A/C
0942000100227801
30% A/C
0942000100227901
SUBHA EDEN-2 — details
Total units
14
Total cost
₹22.73 Cr
Project start
2025-01-01
Proposed completion
2026-12-31
Address
Proposed Residential Apartment at Sy No. 167/1 and 167/2 of Iggaluru Village, Attibele Hobli, Anekal Taluk, , Bengaluru , Anekal , Bengaluru Urban, Karnataka - 562107
VRR GOLDEN ENCLAVE PHASE-III — details
Total units
13
Total cost
₹22.53 Cr
Project start
2024-11-25
Proposed completion
2027-06-30
Address
Sy. No.355, Old Sy. No.155/14, Hulimangala Village, Jigani Hobli, Anekal Taluk, Bengaluru Urban