Compare / Mana Dale vs KEERTHI NANDINI THE ASCENT

Mana Dale vs KEERTHI NANDINI THE ASCENT

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
Mana Dale
Bengaluru Urban · Bengaluru East
1 complaint · 35% built
MANA PROJECTS PVT LTD PRM/KA/RERA/1251/446/PR/220125/007417
On track · 2% built
KEERTHI NANDINI LLP PRM/KA/RERA/1251/446/PR/170326/008533
Mana Dale
Construction
35%
as of Q1 2026-27
Sold
105
of 257 · +26 last qtr
Available
152
KEERTHI NANDINI THE ASCENT
Construction
2%
as of Q4 2025-26
Sold
of 269 · +0 last qtr
Available
269
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Mana Dale
Complaints
1
on this project · 7 on MANA PROJECTS PVT LTD overall
KEERTHI NANDINI THE ASCENT
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
Mana Dale
MANA PROJECTS PVT LTD
3 other projects on K-RERA · 0 delivered (100% complete) · avg 53.0% complete
KEERTHI NANDINI THE ASCENT
KEERTHI NANDINI LLP
No other K-RERA registered projects on file for this promoter.
Mana Dale — escrow account details
Bank
STATE BANK OF INDIA
Branch
IFB Richmond Road, Bangalore
IFSC
SBIN0020743
70% Collection A/C
43569071351
100% A/C
43571831571
30% A/C
43571831286
KEERTHI NANDINI THE ASCENT — escrow account details
Bank
HDFC
Branch
Old Madara Road Branch
IFSC
HDFC0002047
70% Collection A/C
50200118344594
100% A/C
50200118365970
30% A/C
50200116137071
Mana Dale — details
Total units
257
Total cost
₹270.00 Cr
Project start
2025-01-02
Proposed completion
2029-11-30
Address
Sy no 60/1 Kodathi village varthuru hobli Bangalore east taluk
KEERTHI NANDINI THE ASCENT — details
Total units
269
Total cost
₹253.96 Cr
Project start
2026-03-01
Proposed completion
2030-02-28
Address