Compare / Shankara Agraharam Sri Sharadamba Enclave vs TRITON HUMMING VALLEY

Shankara Agraharam Sri Sharadamba Enclave vs TRITON HUMMING VALLEY

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 22% built
Shankara Agraharam PRM/KA/RERA/1254/464/PR/280225/007527
Active
TRITON HOMES LLP PRM/KA/RERA/1254/460/PR/131224/007292
Shankara Agraharam Sri Sharadamba Enclave
Construction
22%
as of Q4 2025-26
Sold
—
of ? · +0 last qtr
Available
0
TRITON HUMMING VALLEY
No quarterly filings found for TRITON HUMMING VALLEY yet — construction progress and sales data aren't available on K-RERA.
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Shankara Agraharam Sri Sharadamba Enclave
Complaints
0
on this project · 4 on Shankara Agraharam overall
TRITON HUMMING VALLEY
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
Shankara Agraharam Sri Sharadamba Enclave
Shankara Agraharam
1 other project on K-RERA
TRITON HUMMING VALLEY
TRITON HOMES LLP
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Shankara Agraharam Sri Sharadamba Enclave
Delay risk no completion progress across filed quarters
TRITON HUMMING VALLEY
No risk signals from filed quarters.
Shankara Agraharam Sri Sharadamba Enclave — escrow account details
Bank
HDFC
Branch
Yelahanka
IFSC
HDFC0004228
70% Collection A/C
50200062091703
100% A/C
50200062091702
30% A/C
50200098397241
TRITON HUMMING VALLEY — escrow account details
Bank
IDFC FIRST BANK
Branch
WHITEFIELD
IFSC
IDFB0080153
70% Collection A/C
10201830326
100% A/C
10201830337
30% A/C
10201830359
Shankara Agraharam Sri Sharadamba Enclave — details
Total cost
₹0.81 Cr
Project start
2024-01-01
Proposed completion
2027-01-01
Address
16/2, 16/4, 18/2 Kasaba Hobli, Sanjevnaryanhalli , Gudibande Taluk, Chikkaballapur , Gudibanda , Chikkaballapura, Karnataka - 561209
TRITON HUMMING VALLEY — details
Total cost
₹0.92 Cr
Project start
2024-12-01
Proposed completion
2025-12-31 overdue
Address
SY NO 159/3 (OLD SY NO 159/1A3), SY NO 159/4 (OLD SY NO 159/1A2) KUDUVATHI VILLAGE, , NANDI HOBLI, , Chikkaballapur , Chikkaballapura, Karnataka - 562103