0 complaints · 13% built
SOBHA LIMITED PRM/KA/RERA/1251/308/PR/230125/007419
On track · 59% built
APG COMMUNITY DEVELOPMENT PRIVATE LIMITED PRM/KA/RERA/1251/310/PR/040226/008450
Sobha Hamptons -Townpark Phase 1 W4 to 6
Construction
13%
as of Q2 2026-27
Sold
230
of 492 · +6 last qtr
Available
266
Assetz Mizumi Reserve Tower A1 A2 A4
Construction
59%
as of Q2 2026-27
Sold
302
of 440 · +16 last qtr
Available
138
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Sobha Hamptons -Townpark Phase 1 W4 to 6
Complaints
0
on this project · 225 on SOBHA LIMITED overall
Assetz Mizumi Reserve Tower A1 A2 A4
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
Sobha Hamptons -Townpark Phase 1 W4 to 6
SOBHA LIMITED
37 other projects on K-RERA · 9 delivered (100% complete) · avg 57.6% complete · 59 complaints across those projects
Assetz Mizumi Reserve Tower A1 A2 A4
APG COMMUNITY DEVELOPMENT PRIVATE LIMITED
1 other project on K-RERA · 0 delivered (100% complete) · avg 59.0% complete
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Sobha Hamptons -Townpark Phase 1 W4 to 6
Promoter pattern 1 of 36 other projects show the same delay-risk pattern
Assetz Mizumi Reserve Tower A1 A2 A4
No risk signals from filed quarters.
Sobha Hamptons -Townpark Phase 1 W4 to 6 — escrow account details
Bank
KOTAK MAHINDRA BANK
Branch
MG Road, Bangalore
IFSC
KKBK0008066
70% Collection A/C
0249886267
100% A/C
0249886281
30% A/C
0249886304
Assetz Mizumi Reserve Tower A1 A2 A4 — escrow account details
Bank
ICICI Bank
Branch
M.G.Road
IFSC
ICIC0000002
70% Collection A/C
625305019757
100% A/C
625305019756
30% A/C
000205038893
Sobha Hamptons -Townpark Phase 1 W4 to 6 — details
Total units
492
Total cost
₹1169.74 Cr
Project start
2025-08-01
Proposed completion
2031-06-30
Address
Proposed residential building plan, Katha no. 80/73/3/74/2/75 (PID NO 150300200400520002), Sy nos 73/3, 74/2, 75 of Thimmegowdana Hosahalli village, Kasaba hobli,Devanahalli Taluk,Bangalore rural,562110
Assetz Mizumi Reserve Tower A1 A2 A4 — details
Total units
440
Total cost
₹834.89 Cr
Project start
2026-01-01
Proposed completion
2030-12-30
Address
AT SY.NO.5/4, 5/5, 173/1, 173/2, 175, 176, 177/1, 177/2, 178, 179/1, 179/2, 180/1, 180/2, 180/3, 187/1, 203 OF KUDLU VILLAGE , AND SY.NO. 5/1 (OLD NO - 5), 6, 7,8/1, 8/4, 8/5 OF PARAPPANA AGRAHARA VILLAGE, BEGUR HOBLI, ANEKAL TALUK, BENGALURU. , Bengaluru South , Bengaluru Urban, Karnataka - 560068