Compare / Mahindra Eden Phase-2 vs Concorde Auriga

Mahindra Eden Phase-2 vs Concorde Auriga

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 5% built
MAHINDRA LIFESPACE DEVELOPERS LIMITED PRM/KA/RERA/1251/310/PR/160425/007668
Concorde Auriga
Bengaluru Urban · Bengaluru South
On track · 13% built
Concorde Housing Corporation Pvt Ltd PRM/KA/RERA/1251/446/PR/210325/007608
Mahindra Eden Phase-2
Construction
5%
as of Q1 2026-27
Sold
103
of 119 · +0 last qtr
Available
16
Concorde Auriga
Construction
13%
as of Q1 2026-27
Sold
20
of 142 · +0 last qtr
Available
122
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Mahindra Eden Phase-2
Complaints
0
on this project · 4 on MAHINDRA LIFESPACE DEVELOPERS LIMITED overall
Concorde Auriga
Complaints
0
on this project · 2 on Concorde Housing Corporation Pvt Ltd overall
Builder track record
Across each promoter's other K-RERA registered projects
Mahindra Eden Phase-2
MAHINDRA LIFESPACE DEVELOPERS LIMITED
3 other projects on K-RERA · 2 delivered (100% complete) · avg 82.3% complete · 3 complaints across those projects
Concorde Auriga
Concorde Housing Corporation Pvt Ltd
7 other projects on K-RERA · 3 delivered (100% complete) · avg 71.5% complete · 1 complaint across those projects
Mahindra Eden Phase-2 — escrow account details
Bank
Axis Bank
Branch
Nitesh Times Square Building No.08, 3rd Floor, M.G. Road, Bangalore
IFSC
UTIB0001541
70% Collection A/C
924020041421889
100% A/C
924020041421928
30% A/C
919020087032388
Concorde Auriga — escrow account details
Bank
Karnataka Bank Ltd.
Branch
Kasturba Road
IFSC
KARB0000083
70% Collection A/C
0083202500002001
100% A/C
0083202500001901
30% A/C
0083202500002101
Mahindra Eden Phase-2 — details
Total units
119
Total cost
₹193.14 Cr
Project start
2025-03-01
Proposed completion
2029-12-28
Address
Mahindra Eden Sy. No. 49 & 50/2, Holiday Village Road, Vajarahalli Village, Kanakapura Road, Bengaluru: 560062.
Concorde Auriga — details
Total units
142
Total cost
₹221.94 Cr
Project start
2025-04-15
Proposed completion
2030-12-31
Address
Sy No.31/2B, 34/1 & 35, Medihalli Village, Bidarahalli Hobli, Bangalore East