FOURWALLS BHUVI vs Castle Green
Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
FOURWALLS BHUVI
Dakshina Kannada · Mangalore
On track · 46% built
FOURWALLS BUILDERS & DEVELOPERS
PRM/KA/RERA/1257/334/PR/140525/007744
Castle Green
Dakshina Kannada · Mangalore
On track · 5% built
Nidhi Land Infrastructure Developers India (P) Ltd , Karunakara Shetty & K Vimal Kumar
PRM/KA/RERA/1257/334/PR/200626/008733
FOURWALLS BHUVI
Construction
46%
as of Q1 2026-27
Sold
5
of 14
· +0 last qtr
Available
9
Castle Green
Construction
5%
as of Q1 2026-27
Sold
2
of 14
· +2 last qtr
Available
12
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
FOURWALLS BHUVI
Complaints
0
on this project
Castle Green
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
FOURWALLS BHUVI
FOURWALLS BUILDERS & DEVELOPERS
1 other project on K-RERA
· 0 delivered (100% complete)
· avg 69.0% complete
Castle Green
Nidhi Land Infrastructure Developers India (P) Ltd , Karunakara Shetty & K Vimal Kumar
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
FOURWALLS BHUVI
Delay risk
trending ~13 month(s) past declared completion
Promoter pattern
1 of 1 other projects show the same delay-risk pattern
Castle Green
No risk signals from filed quarters.
FOURWALLS BHUVI — escrow account details
Castle Green — escrow account details
FOURWALLS BHUVI — details
Castle Green — details