SATTVA SPRINGS vs After The Rain Phase III
Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
SATTVA SPRINGS
Bengaluru Urban · Bengaluru North
On track · 36% built
Sattva Resi Private Limited
PRM/KA/RERA/1251/310/PR/240724/006948
After The Rain Phase III
Bengaluru Urban · Bengaluru North
On track · 17% built
TOTAL ENVIRONMENT BUILDING SYSTEMS PVT LTD
PRM/KA/RERA/1251/309/PR/160825/008002
SATTVA SPRINGS
Construction
36%
as of Q1 2026-27
Sold
26
of 66
· +1 last qtr
Available
40
After The Rain Phase III
Construction
17%
as of Q1 2026-27
Sold
31
of 36
· +31 last qtr
Available
5
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
SATTVA SPRINGS
Complaints
0
on this project · 2 on Sattva Resi Private Limited overall
After The Rain Phase III
Complaints
0
on this project · 14 on TOTAL ENVIRONMENT BUILDING SYSTEMS PVT LTD overall
Builder track record
Across each promoter's other K-RERA registered projects
SATTVA SPRINGS
Sattva Resi Private Limited
7 other projects on K-RERA
· 1 delivered (100% complete)
· avg 30.3% complete
· 2 complaints across those projects
After The Rain Phase III
TOTAL ENVIRONMENT BUILDING SYSTEMS PVT LTD
1 other project on K-RERA
· 0 delivered (100% complete)
· avg 5.0% complete
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
SATTVA SPRINGS
Delay risk
trending ~34 month(s) past declared completion
Promoter pattern
3 of 6 other projects show the same delay-risk pattern
After The Rain Phase III
Delay risk
no completion progress across filed quarters
Escrow
2 quarter(s) withdrawn with no matching progress
SATTVA SPRINGS — escrow account details
After The Rain Phase III — escrow account details
SATTVA SPRINGS — details
After The Rain Phase III — details