Compare / Shankara Agraharam Sri Sharadamba Enclave vs HMR ANANDA GREENS

Shankara Agraharam Sri Sharadamba Enclave vs HMR ANANDA GREENS

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 22% built
Shankara Agraharam PRM/KA/RERA/1254/464/PR/280225/007527
HMR ANANDA GREENS
Mysore · Bengaluru North
Active
CHAMUNDESHWARI LAKSHMI ESTATES PRM/KA/RERA/1268/378/PR/110625/007815
Shankara Agraharam Sri Sharadamba Enclave
Construction
22%
as of Q4 2025-26
Sold
of ? · +0 last qtr
Available
0
HMR ANANDA GREENS
No quarterly filings found for HMR ANANDA GREENS yet — construction progress and sales data aren't available on K-RERA.
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Shankara Agraharam Sri Sharadamba Enclave
Complaints
0
on this project · 4 on Shankara Agraharam overall
HMR ANANDA GREENS
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
Shankara Agraharam Sri Sharadamba Enclave
Shankara Agraharam
1 other project on K-RERA
HMR ANANDA GREENS
CHAMUNDESHWARI LAKSHMI ESTATES
1 other project on K-RERA
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Shankara Agraharam Sri Sharadamba Enclave
Delay risk no completion progress across filed quarters
HMR ANANDA GREENS
No risk signals from filed quarters.
Shankara Agraharam Sri Sharadamba Enclave — escrow account details
Bank
HDFC
Branch
Yelahanka
IFSC
HDFC0004228
70% Collection A/C
50200062091703
100% A/C
50200062091702
30% A/C
50200098397241
HMR ANANDA GREENS — escrow account details
Bank
KOTAK MAHINDRA BANK
Branch
Siddarthanagar Branch
IFSC
KKBK0008283
70% Collection A/C
7450802017
100% A/C
7450802000
30% A/C
7450801997
Shankara Agraharam Sri Sharadamba Enclave — details
Total cost
₹0.81 Cr
Project start
2024-01-01
Proposed completion
2027-01-01
Address
16/2, 16/4, 18/2 Kasaba Hobli, Sanjevnaryanhalli , Gudibande Taluk, Chikkaballapur , Gudibanda , Chikkaballapura, Karnataka - 561209
HMR ANANDA GREENS — details
Total cost
₹1.11 Cr
Project start
2024-07-16
Proposed completion
2026-03-31 overdue
Address
62/3, 62/4, 62/5 and 62/11, Manuganahalli Village, Bilikere Hobli, Hunsur Taluk, Mysore District, Mysore