JR GREENWICH PHASE III vs Swarna Griha - 3

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
Delivered · 100% built
JR HOUSING DEVELOPERS PVT LTD PRM/KA/RERA/1251/308/PR/210524/006915
Swarna Griha - 3
Kolar · Bengaluru East
On track · 65% built
FELICITY ADOBE LLP PRM/KA/RERA/1265/339/PR/110925/008088
JR GREENWICH PHASE III
Construction
100%
as of Q3 2025-26
Sold
of ? · +0 last qtr
Available
0
Swarna Griha - 3
Construction
65%
as of Q1 2026-27
Sold
of ? · +0 last qtr
Available
0
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
JR GREENWICH PHASE III
Complaints
0
on this project
Swarna Griha - 3
Complaints
0
on this project · 6 on FELICITY ADOBE LLP overall
Builder track record
Across each promoter's other K-RERA registered projects
JR GREENWICH PHASE III
JR HOUSING DEVELOPERS PVT LTD
1 other project on K-RERA
Swarna Griha - 3
FELICITY ADOBE LLP
2 other projects on K-RERA · 1 delivered (100% complete) · avg 78.5% complete
JR GREENWICH PHASE III — escrow account details
Bank
Karnataka Bank Ltd.
Branch
NEHRUNAGAR
IFSC
KARB0000063
70% Collection A/C
1302000100102301
100% A/C
1302000100102201
30% A/C
1302000100102401
Swarna Griha - 3 — escrow account details
Bank
Canara Bank
Branch
Trinity Circle
IFSC
CNRB0000792
70% Collection A/C
120037753776
100% A/C
120037703780
30% A/C
120037090557
JR GREENWICH PHASE III — details
Total cost
₹5.61 Cr
Project start
2023-12-30
Proposed completion
2028-11-20
Address
Next to Wipro Office, Kodathi Village, Varthuru Hobli, Bengaluru,
Swarna Griha - 3 — details
Total cost
₹3.72 Cr
Project start
2025-07-01
Proposed completion
2027-06-30
Address
Survey no 20/1 Arabhikothanur Village, Vakkaleri Hobli Kolar Taluk and District