Compare / SILVER KITES - ELITE vs Eesha Eden

SILVER KITES - ELITE vs Eesha Eden

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
0 complaints · 100% built
ESSENN INFRA TOWNSHIP PRIVATE LIMITED PRM/KA/RERA/1254/465/PR/220923/006287
Eesha Eden
Mysore · Bengaluru South
Active
NCORP ENTERPRISES LLP PRM/KA/RERA/1268/378/PR/261125/008275
SILVER KITES - ELITE
Construction
100%
as of Q4 2025-26
Sold
of ? · +0 last qtr
Available
0
Eesha Eden
No quarterly filings found for Eesha Eden yet — construction progress and sales data aren't available on K-RERA.
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
SILVER KITES - ELITE
Complaints
0
on this project · 27 on ESSENN INFRA TOWNSHIP PRIVATE LIMITED overall
Eesha Eden
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
SILVER KITES - ELITE
ESSENN INFRA TOWNSHIP PRIVATE LIMITED
2 other projects on K-RERA · 2 delivered (100% complete) · avg 100.0% complete · 28 complaints across those projects
Eesha Eden
NCORP ENTERPRISES LLP
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
SILVER KITES - ELITE
No risk signals from filed quarters.
Eesha Eden
No risk signals from filed quarters.
SILVER KITES - ELITE — escrow account details
Bank
Punjab National Bank
Branch
Jayanagar
IFSC
PUNB0099010
70% Collection A/C
0990102900000013
100% A/C
0990102900000022
30% A/C
0990102100000192
Eesha Eden — escrow account details
Bank
ICICI Bank
Branch
Jayanagar 3rd Block
IFSC
ICIC0000053
70% Collection A/C
005305014382
100% A/C
005305014381
30% A/C
005305013622
SILVER KITES - ELITE — details
Total cost
₹34.03 Cr
Project start
2023-08-03
Proposed completion
2026-06-30
Address
Sy.Nos.8/1, 8/2, 8/3, 8/4, 8/5, 8/6, 8/7, 8/8, 8/9, 8/10, 8/11, 8/12, 8/14, 9/1, 9/2 of Nadipinayakanahalli Village , & Sy.Nos.64/1, 64/2, 65, 66, 67, 68, 69 of Nallenahalli Village & Sy.No.62/3 & 67/5 of Thaduru Village, Jangamakote Hobli, Shidlaghatta Taluk & Chikka , Sidlaghatta , Chikkaballapura, Karnataka - 562102
Eesha Eden — details
Total cost
₹33.50 Cr
Project start
2025-08-01
Proposed completion
2028-08-31
Address
Sy No 94/1 and 108/1 of Lingabudi Village , Kasaba Hobli , MYSORE , Mysore, Karnataka - 570023