Compare / SOULSPRING PHASE 1 vs ADARSH PALM ACRES PHASE 3

SOULSPRING PHASE 1 vs ADARSH PALM ACRES PHASE 3

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 57% built
SHANKESHWAR LANDMARK LLP PRM/KA/RERA/1251/310/PR/220223/005735
On track · 2% built
Adarsh Nivaas Private Limited PRM/KA/RERA/1251/309/PR/181025/008181
SOULSPRING PHASE 1
Construction
57%
as of Q1 2026-27
Sold
165
of 172 · +2 last qtr
Available
67
ADARSH PALM ACRES PHASE 3
Construction
2%
as of Q1 2026-27
Sold
37
of 196 · +0 last qtr
Available
159
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
SOULSPRING PHASE 1
Complaints
0
on this project
ADARSH PALM ACRES PHASE 3
Complaints
0
on this project · 3 on Adarsh Nivaas Private Limited overall
Builder track record
Across each promoter's other K-RERA registered projects
SOULSPRING PHASE 1
SHANKESHWAR LANDMARK LLP
1 other project on K-RERA · 0 delivered (100% complete) · avg 21.0% complete
ADARSH PALM ACRES PHASE 3
Adarsh Nivaas Private Limited
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
SOULSPRING PHASE 1
Delay risk trending ~4 month(s) past declared completion
Escrow 1 quarter(s) withdrawn with no matching progress
Promoter pattern 1 of 1 other projects show the same delay-risk pattern
ADARSH PALM ACRES PHASE 3
Escrow 1 quarter(s) withdrawn with no matching progress
SOULSPRING PHASE 1 — escrow account details
Bank
Indian Bank
Branch
Richmond Circle
IFSC
IDIB000R018
70% Collection A/C
7316853156
ADARSH PALM ACRES PHASE 3 — escrow account details
Bank
Union Bank of India
Branch
Kasturba Road, Bangalore
IFSC
UBIN0550230
70% Collection A/C
502301010035266
100% A/C
502301010035265
30% A/C
502301010035264
SOULSPRING PHASE 1 — details
Total units
172
Total cost
₹473.83 Cr
Project start
2023-02-01
Proposed completion
2028-12-31
Address
SY. NO. 102/2, YARANDAHALLI VILLAGE, JIGINI HOBLI ,ANEKAL TALUK, ANEKAL, BENGALURU URBAN, KARNATAKA
ADARSH PALM ACRES PHASE 3 — details
Total units
196
Total cost
₹579.47 Cr
Project start
2025-09-10
Proposed completion
2031-09-30
Address
Sy.no.196,197,198 & 199 , GhattihalliVillage Bengaluru Urban , Anekal ,Bengaluru Urban, Karnataka - 560099 ,Anekal , Bengaluru Urban, Karnataka -