Sobha Royal Crest vs SUMADHURA SOLACE PHASE-II
Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
Sobha Royal Crest
Bengaluru Urban · Bengaluru East
2 complaints · 60% built
SOBHA LIMITED
PRM/KA/RERA/1251/309/PR/300522/004936
SUMADHURA SOLACE PHASE-II
Bengaluru Urban · Bengaluru East
On track · 30% built
SUMADHURA INFRACON PRIVATE LIMITED
PRM/KA/RERA/1251/446/PR/111225/008333
Sobha Royal Crest
Construction
60%
as of Q1 2026-27
Sold
329
of 329
· +0 last qtr
Available
0
SUMADHURA SOLACE PHASE-II
Construction
30%
as of Q1 2026-27
Sold
—
of 329
· +0 last qtr
Available
331
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Sobha Royal Crest
Complaints
2
on this project · 224 on SOBHA LIMITED overall
SUMADHURA SOLACE PHASE-II
Complaints
0
on this project · 4 on SUMADHURA INFRACON PRIVATE LIMITED overall
Builder track record
Across each promoter's other K-RERA registered projects
Sobha Royal Crest
SOBHA LIMITED
36 other projects on K-RERA
· 9 delivered (100% complete)
· avg 52.3% complete
· 53 complaints across those projects
SUMADHURA SOLACE PHASE-II
SUMADHURA INFRACON PRIVATE LIMITED
13 other projects on K-RERA
· 0 delivered (100% complete)
· avg 51.7% complete
· 3 complaints across those projects
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Sobha Royal Crest
Delay risk
no completion progress across filed quarters
Escrow
2 quarter(s) withdrawn with no matching progress
Promoter pattern
1 of 35 other projects show the same delay-risk pattern
SUMADHURA SOLACE PHASE-II
Delay risk
construction progress far too slow to plausibly hit declared completion
Promoter pattern
8 of 11 other projects show the same delay-risk pattern
Sobha Royal Crest — escrow account details
SUMADHURA SOLACE PHASE-II — escrow account details
Sobha Royal Crest — details
SUMADHURA SOLACE PHASE-II — details