Compare / Sobha Sentosa Phase 2 Wing 5 and 6 vs THE LOFT

Sobha Sentosa Phase 2 Wing 5 and 6 vs THE LOFT

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
13 complaints · 100% built
SOBHA LIMITED PRM/KA/RERA/1251/446/PR/310322/004797
THE LOFT
Bengaluru Urban · Bengaluru East
On track · 17% built
VRISE CONSTRUCTIONS LLP PRM/KA/RERA/1251/446/PR/070126/008387
Sobha Sentosa Phase 2 Wing 5 and 6
Construction
100%
as of Q1 2026-27
Sold
140
of 142 · +0 last qtr
Available
2
THE LOFT
Construction
17%
as of Q1 2026-27
Sold
25
of 144 · +12 last qtr
Available
119
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Sobha Sentosa Phase 2 Wing 5 and 6
Complaints
13
on this project · 224 on SOBHA LIMITED overall
THE LOFT
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
Sobha Sentosa Phase 2 Wing 5 and 6
SOBHA LIMITED
36 other projects on K-RERA · 8 delivered (100% complete) · avg 51.2% complete · 42 complaints across those projects
THE LOFT
VRISE CONSTRUCTIONS LLP
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Sobha Sentosa Phase 2 Wing 5 and 6
Promoter pattern 2 of 35 other projects show the same delay-risk pattern
THE LOFT
Delay risk construction progress far too slow to plausibly hit declared completion
Sobha Sentosa Phase 2 Wing 5 and 6 — escrow account details
Bank
ICICI Bank
Branch
ICICI Towers, 1 Commissariat Road,,Bangalore
IFSC
ICIC0000002
70% Collection A/C
777705220595
THE LOFT — escrow account details
Bank
KOTAK MAHINDRA BANK
Branch
Whitefield Branch
IFSC
KKBK0008042
70% Collection A/C
3551112987
100% A/C
3551112970
30% A/C
3551112963
Sobha Sentosa Phase 2 Wing 5 and 6 — details
Total units
142
Total cost
₹170.23 Cr
Project start
2023-01-01
Proposed completion
2026-12-31
Address
Whitefield, Bangalore
THE LOFT — details
Total units
144
Total cost
₹195.30 Cr
Project start
2025-12-01
Proposed completion
2029-12-31
Address
KATHA NO. 839, SY NO. 118/1 & 118/2, CHANNASANDRA VILLAGE, , BIDARAHALLI HOBLI, MAHADEVAPURA ZONE, WARD NO. 83 , Bengaluru East , Bengaluru Urban, Karnataka - 560067