Compare / Assetz Mizumi Reserve Tower A1 A2 A4 vs Eaton Park @ The Prestige City

Assetz Mizumi Reserve Tower A1 A2 A4 vs Eaton Park @ The Prestige City

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 54% built
APG COMMUNITY DEVELOPMENT PRIVATE LIMITED PRM/KA/RERA/1251/310/PR/040226/008450
On track · 2% built
PRESTIGE PROJECTS PRIVATE LIMITED PRM/KA/RERA/1251/308/PR/180326/008537
Assetz Mizumi Reserve Tower A1 A2 A4
Construction
54%
as of Q1 2026-27
Sold
286
of 440 · +11 last qtr
Available
154
Eaton Park @ The Prestige City
Construction
2%
as of Q1 2026-27
Sold
167
of 366 · +55 last qtr
Available
199
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Assetz Mizumi Reserve Tower A1 A2 A4
Complaints
0
on this project
Eaton Park @ The Prestige City
Complaints
0
on this project · 11 on PRESTIGE PROJECTS PRIVATE LIMITED overall
Builder track record
Across each promoter's other K-RERA registered projects
Assetz Mizumi Reserve Tower A1 A2 A4
APG COMMUNITY DEVELOPMENT PRIVATE LIMITED
1 other project on K-RERA · 0 delivered (100% complete) · avg 49.0% complete
Eaton Park @ The Prestige City
PRESTIGE PROJECTS PRIVATE LIMITED
7 other projects on K-RERA · 1 delivered (100% complete) · avg 72.3% complete · 5 complaints across those projects
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Assetz Mizumi Reserve Tower A1 A2 A4
No risk signals from filed quarters.
Eaton Park @ The Prestige City
Escrow 1 quarter(s) withdrawn with no matching progress
Promoter pattern 4 of 6 other projects show the same delay-risk pattern
Assetz Mizumi Reserve Tower A1 A2 A4 — escrow account details
Bank
ICICI Bank
Branch
M.G.Road
IFSC
ICIC0000002
70% Collection A/C
625305019757
100% A/C
625305019756
30% A/C
000205038893
Eaton Park @ The Prestige City — escrow account details
Bank
ICICI Bank
Branch
M G Road Bengaluru
IFSC
ICIC0000002
70% Collection A/C
777705283829
100% A/C
777705293930
30% A/C
777705191222
Assetz Mizumi Reserve Tower A1 A2 A4 — details
Total units
440
Total cost
₹834.89 Cr
Project start
2026-01-01
Proposed completion
2030-12-30
Address
AT SY.NO.5/4, 5/5, 173/1, 173/2, 175, 176, 177/1, 177/2, 178, 179/1, 179/2, 180/1, 180/2, 180/3, 187/1, 203 OF KUDLU VILLAGE , AND SY.NO. 5/1 (OLD NO - 5), 6, 7,8/1, 8/4, 8/5 OF PARAPPANA AGRAHARA VILLAGE, BEGUR HOBLI, ANEKAL TALUK, BENGALURU. , Bengaluru South , Bengaluru Urban, Karnataka - 560068
Eaton Park @ The Prestige City — details
Total units
366
Total cost
₹718.11 Cr
Project start
2026-04-01
Proposed completion
2030-06-30
Address
Y. NO. 31/2, 32/1, 32/2, 32/3 AND 32/5 OF VK HALLI VILLAGE, SARJAPUR HOBLI ANEKUL TALUK BENGALURU, ANEKAL, BENGALURU URBAN, KARNATAKA - 562125