Compare / Provident Equinox 5 vs SATTVA SONGBIRD PH 2

Provident Equinox 5 vs SATTVA SONGBIRD PH 2

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
0 complaints
Provident Housing Limited PRM/KA/RERA/1251/310/PR/170126/008410
On track · 3% built
Sattva Resi Private Limited PRM/KA/RERA/1251/310/PR/270326/008557
Provident Equinox 5
No quarterly filings found for Provident Equinox 5 yet — construction progress and sales data aren't available on K-RERA.
SATTVA SONGBIRD PH 2
Construction
3%
as of Q1 2026-27
Sold
43
of 381 · +43 last qtr
Available
209
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Provident Equinox 5
Complaints
0
on this project · 32 on Provident Housing Limited overall
SATTVA SONGBIRD PH 2
Complaints
0
on this project · 2 on Sattva Resi Private Limited overall
Builder track record
Across each promoter's other K-RERA registered projects
Provident Equinox 5
Provident Housing Limited
3 other projects on K-RERA · 0 delivered (100% complete) · avg 14.0% complete · 2 complaints across those projects
SATTVA SONGBIRD PH 2
Sattva Resi Private Limited
7 other projects on K-RERA · 1 delivered (100% complete) · avg 35.8% complete · 2 complaints across those projects
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Provident Equinox 5
No risk signals from filed quarters.
SATTVA SONGBIRD PH 2
Promoter pattern 4 of 6 other projects show the same delay-risk pattern
Provident Equinox 5 — escrow account details
Bank
ICICI Bank
Branch
Ulsoor Road Branch
IFSC
ICIC0003904
70% Collection A/C
777705139341
100% A/C
777705129340
30% A/C
777705149349
SATTVA SONGBIRD PH 2 — escrow account details
Bank
ICICI Bank
Branch
Commissariat Road
IFSC
ICIC0000002
70% Collection A/C
777705323028
100% A/C
777705323027
30% A/C
777705323029
Provident Equinox 5 — details
Total units
396
Total cost
₹337.96 Cr
Project start
2026-03-02
Proposed completion
2030-03-31
Address
Venkatapura Village Kengeri Hobli Bangalore South
SATTVA SONGBIRD PH 2 — details
Total units
381
Total cost
₹308.31 Cr
Project start
2026-05-01
Proposed completion
2031-06-27
Address