Compare / Sobha Madison Heights-Townpark Phase 2 W1 to 4 vs SATTVA AANGANE

Sobha Madison Heights-Townpark Phase 2 W1 to 4 vs SATTVA AANGANE

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
0 complaints · 20% built
SOBHA LIMITED PRM/KA/RERA/1251/308/PR/230125/007421
SATTVA AANGANE
Bengaluru Urban · Bengaluru East
No quarterly filings
Sattva Resi Private Limited PRM/KA/RERA/1251/446/PR/180926/008944
Sobha Madison Heights-Townpark Phase 2 W1 to 4
Construction
20%
as of Q1 2026-27
Sold
540
of 640 · +6 last qtr
Available
100
SATTVA AANGANE
No quarterly filings found for SATTVA AANGANE yet — construction progress and sales data aren't available on K-RERA.
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Sobha Madison Heights-Townpark Phase 2 W1 to 4
Complaints
0
on this project · 224 on SOBHA LIMITED overall
SATTVA AANGANE
Complaints
0
on this project · 2 on Sattva Resi Private Limited overall
Builder track record
Across each promoter's other K-RERA registered projects
Sobha Madison Heights-Townpark Phase 2 W1 to 4
SOBHA LIMITED
36 other projects on K-RERA · 9 delivered (100% complete) · avg 53.5% complete · 55 complaints across those projects
SATTVA AANGANE
Sattva Resi Private Limited
7 other projects on K-RERA · 1 delivered (100% complete) · avg 31.1% complete · 2 complaints across those projects
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Sobha Madison Heights-Townpark Phase 2 W1 to 4
Promoter pattern 2 of 35 other projects show the same delay-risk pattern
SATTVA AANGANE
Promoter pattern 4 of 7 other projects show the same delay-risk pattern
Sobha Madison Heights-Townpark Phase 2 W1 to 4 — escrow account details
Bank
KOTAK MAHINDRA BANK
Branch
MG Road, Bangalore
IFSC
KKBK0008066
70% Collection A/C
0249886328
100% A/C
0249886342
30% A/C
0249886359
SATTVA AANGANE — escrow account details
Bank
ICICI Bank
Branch
Commissariat Road
IFSC
ICIC0000002
70% Collection A/C
777705323022
100% A/C
777705323021
30% A/C
777705323023
Sobha Madison Heights-Townpark Phase 2 W1 to 4 — details
Total units
640
Total cost
₹1126.78 Cr
Project start
2026-02-01
Proposed completion
2032-12-31
Address
Sy No. 54/3, 55/1, 55/2, 58/1, 58/2, 58/3, 59/2, 59/3, 59/4, 59/5, 60/2, 61, 63/1 Hadosiddapura Village, and Sy. No 31/1 Chikkannelli Village
SATTVA AANGANE — details
Total units
625
Total cost
₹1106.99 Cr
Project start
2026-10-01
Proposed completion
2032-10-21
Address