Compare / DISHA PURSUIT OF THE ELEMENTS PHASE 1 vs CANDEUR ICON PHASE II

DISHA PURSUIT OF THE ELEMENTS PHASE 1 vs CANDEUR ICON PHASE II

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 73% built
Dishahabitat Projects LLP PRM/KA/RERA/1251/308/PR/280324/006756
No quarterly filings
M/s CANDEUR CONSTRUCTIONS PRM/KA/RERA/1251/446/PR/311026/009067
DISHA PURSUIT OF THE ELEMENTS PHASE 1
Construction
73%
as of Q2 2026-27
Sold
663
of 843 · +16 last qtr
Available
180
CANDEUR ICON PHASE II
No quarterly filings found for CANDEUR ICON PHASE II yet — construction progress and sales data aren't available on K-RERA.
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
DISHA PURSUIT OF THE ELEMENTS PHASE 1
Complaints
0
on this project
CANDEUR ICON PHASE II
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
DISHA PURSUIT OF THE ELEMENTS PHASE 1
Dishahabitat Projects LLP
1 other project on K-RERA · 0 delivered (100% complete) · avg 34.0% complete
CANDEUR ICON PHASE II
M/s CANDEUR CONSTRUCTIONS
1 other project on K-RERA
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
DISHA PURSUIT OF THE ELEMENTS PHASE 1
Escrow 1 quarter(s) withdrawn with no matching progress
Promoter pattern 1 of 1 other projects show the same delay-risk pattern
CANDEUR ICON PHASE II
No risk signals from filed quarters.
DISHA PURSUIT OF THE ELEMENTS PHASE 1 — escrow account details
Bank
Axis Bank
Branch
WHITEFIELD MAIN ROAD
IFSC
UTIB0002177
70% Collection A/C
924020002468029
100% A/C
924020002507597
30% A/C
923020023902257
CANDEUR ICON PHASE II — escrow account details
Bank
FEDERAL BANK OF INDIA
Branch
Kadathi Gate
IFSC
FDRL0002171
70% Collection A/C
217102000008562
100% A/C
217102000008570
30% A/C
217102000008554
DISHA PURSUIT OF THE ELEMENTS PHASE 1 — details
Total units
843
Total cost
₹557.55 Cr
Project start
2024-01-01
Proposed completion
2027-12-31
Address
SY. NO. 210, MANDUR VILLAGE, KATHA NO. 264/110, E-KHATHA NO. 150200401600800257, BIDARAHALLI HOBLI, BANGALORE EAST TALUK , Bengaluru East
CANDEUR ICON PHASE II — details
Total units
856
Total cost
₹649.77 Cr
Project start
2026-08-01
Proposed completion
2032-08-01
Address
SY NO 168/1A,1B,3,4,9,11,12,13, 169/3&4, 170/1A,1B,3,4,5,6, 171/5,6,8,9,13,15,16, 173/4-8, 174/1A,1B,2, 175, 176/3,4,5,6A,6B,6C,7,8,9 , 177/1-11,13-16, 178/1A&1B, 185/1&2, 186/2-7, 188/3A,3B,8,10-21, 214/5,16,17 OF GUNJURU VILLAGE, VARTHUR HOBLI, VARTHUR, JCR LAYOUT, WARD NO. 149 , Bengaluru East , Bengaluru Urban, Karnataka - 560087