Sharadindu Stage IV
Mandya · Bengaluru North
On track · 51% built
Sree Senior Homes PRM/KA/RERA/1267/375/PR/280324/006739
Active
KNS Infrastructure Private Limited PRM/KA/RERA/1251/310/PR/220626/008739
Sharadindu Stage IV
Construction
51%
as of Q1 2026-27
Sold
19
of 24 · +2 last qtr
Available
5
KNS Anirvan Phase III
No quarterly filings found for KNS Anirvan Phase III yet — construction progress and sales data aren't available on K-RERA.
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Sharadindu Stage IV
Complaints
0
on this project · 1 on Sree Senior Homes overall
KNS Anirvan Phase III
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
Sharadindu Stage IV
Sree Senior Homes
No other K-RERA registered projects on file for this promoter.
KNS Anirvan Phase III
KNS Infrastructure Private Limited
3 other projects on K-RERA · 1 delivered (100% complete) · avg 100.0% complete
Sharadindu Stage IV — escrow account details
Bank
South Indian Bank Ltd.
Branch
Brigade Road
IFSC
SIBL0000108
70% Collection A/C
0108073000001885
100% A/C
0108073000001890
30% A/C
0108073000001883
KNS Anirvan Phase III — escrow account details
Bank
HDFC
Branch
RICHMOND ROAD, BENGALURU
IFSC
HDFC0000523
70% Collection A/C
57500001976171
100% A/C
57500001975382
30% A/C
57500001974774
Sharadindu Stage IV — details
Total units
24
Total cost
₹7.15 Cr
Project start
2024-03-08
Proposed completion
2030-01-31
Address
Khatha 254, Ranganakoppalu Village, Kasaba Hobli, Pandavapura Taluk, Mandya District
KNS Anirvan Phase III — details
Total cost
₹7.77 Cr
Project start
2026-05-18
Proposed completion
2031-05-22
Address