Compare / High Life Towers vs ZENITH HEIGHTS

High Life Towers vs ZENITH HEIGHTS

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
High Life Towers
Bengaluru Urban · Bengaluru North
On track · 46% built
MEENAKSHI INFRRA PROJECTS PRM/KA/RERA/1251/309/PR/200923/006268
ZENITH HEIGHTS
Bengaluru Urban · Bengaluru North
On track · 1% built
DWARAKAMAI BUILDERS AND DEVELOPERS PRIVATE LIMITED PRM/KA/RERA/1251/446/PR/230626/008748
High Life Towers
Construction
46%
as of Q1 2026-27
Sold
62
of 198 · +4 last qtr
Available
251
ZENITH HEIGHTS
Construction
1%
as of Q1 2026-27
Sold
—
of 140 · +0 last qtr
Available
140
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
High Life Towers
Complaints
0
on this project
ZENITH HEIGHTS
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
High Life Towers
MEENAKSHI INFRRA PROJECTS
No other K-RERA registered projects on file for this promoter.
ZENITH HEIGHTS
DWARAKAMAI BUILDERS AND DEVELOPERS PRIVATE LIMITED
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
High Life Towers
Delay risk construction progress far too slow to plausibly hit declared completion
ZENITH HEIGHTS
No risk signals from filed quarters.
High Life Towers — escrow account details
Bank
Axis Bank
Branch
HEGDENAGAR
IFSC
UTIB0002980
70% Collection A/C
922020044798461
ZENITH HEIGHTS — escrow account details
Bank
INDUSIND BANK
Branch
AECS layout
IFSC
INDB0001454
70% Collection A/C
252303808886
100% A/C
252303808887
30% A/C
252303808888
High Life Towers — details
Total units
198
Total cost
₹200.48 Cr
Project start
2022-05-18
Proposed completion
2027-08-05
Address
Property No./PID No. 2834/81/2a,81/2b ,rachenahalli village , Kr Purma Hobli Bengaluru , Bengaluru North , Bengaluru Urban, Karnataka - 560045
ZENITH HEIGHTS — details
Total units
140
Total cost
₹198.62 Cr
Project start
2026-05-06
Proposed completion
2029-12-31
Address
Sy No- 176/3 , Kannamangala Village, near water tank