Compare / Birla Ojasvi vs ABHEE CITY URBAN GLENN PHASE II

Birla Ojasvi vs ABHEE CITY URBAN GLENN PHASE II

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
Birla Ojasvi
Bengaluru Urban · Bengaluru North
On track · 18% built
Birla Estates Private Limited PRM/KA/RERA/1251/310/PR/040924/006989
No quarterly filings
ABHEE VENTURES PRIVATE LIMITED PRM/KA/RERA/1251/308/PR/300926/008986
Birla Ojasvi
Construction
18%
as of Q1 2026-27
Sold
560
of 615 · +9 last qtr
Available
55
ABHEE CITY URBAN GLENN PHASE II
No quarterly filings found for ABHEE CITY URBAN GLENN PHASE II yet — construction progress and sales data aren't available on K-RERA.
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Birla Ojasvi
Complaints
0
on this project · 3 on Birla Estates Private Limited overall
ABHEE CITY URBAN GLENN PHASE II
Complaints
0
on this project · 1 on ABHEE VENTURES PRIVATE LIMITED overall
Builder track record
Across each promoter's other K-RERA registered projects
Birla Ojasvi
Birla Estates Private Limited
No other K-RERA registered projects on file for this promoter.
ABHEE CITY URBAN GLENN PHASE II
ABHEE VENTURES PRIVATE LIMITED
8 other projects on K-RERA · 1 delivered (100% complete) · avg 63.4% complete
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Birla Ojasvi
Delay risk construction progress far too slow to plausibly hit declared completion
ABHEE CITY URBAN GLENN PHASE II
No risk signals from filed quarters.
Birla Ojasvi — escrow account details
Bank
ICICI Bank
Branch
MG Road
IFSC
ICIC0000002
70% Collection A/C
777705250035
100% A/C
777705250034
30% A/C
777705250036
ABHEE CITY URBAN GLENN PHASE II — escrow account details
Bank
HDFC
Branch
Kasturba Road Branch, Bangalore
IFSC
HDFC0000009
70% Collection A/C
57500001999257
100% A/C
57500002000265
30% A/C
57500001999872
Birla Ojasvi — details
Total units
615
Total cost
₹635.14 Cr
Project start
2025-01-12
Proposed completion
2031-01-11
Address
Birla Trimaya, B.K. Halli Road, Akkalenahalli-Mallenahalli Village, Devanahalli Taluk, Bangalore Rural District-562110
ABHEE CITY URBAN GLENN PHASE II — details
Total units
1000
Total cost
₹784.03 Cr
Project start
2026-07-10
Proposed completion
2033-12-31
Address
ABHEE AARIA, SY.NO:58/1, 58/2, 58/3, 58/4, 58/5, 58/6, 58/7, 58/9, 58/12,58/13, 302/2, 302/3A1(NEW SY.NO.302/7), 302/3A2, 302/5 & 302/6, GUNJURVILLAGE VARTHUR HOBLI, BANGALORE EAST TALUK, WARD NO.149,BANGALORE, BENGALURU NORTH, BENGALURU URBAN, KARNATAKA - 560087