Compare / PLATINUM EAST WOODS vs PSR VANASREE PHASE-III

PLATINUM EAST WOODS vs PSR VANASREE PHASE-III

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 62% built
PLATINUM - NARYA INFRA PRM/KA/RERA/1251/446/PR/100423/005855
No quarterly filings
M/s PSR BUILDERS AND DEVELOPERS PRM/KA/RERA/1251/446/PR/171126/009102
PLATINUM EAST WOODS
Construction
62%
as of Q3 2025-26
Sold
88
of 188 · +88 last qtr
Available
100
PSR VANASREE PHASE-III
No quarterly filings found for PSR VANASREE PHASE-III yet — construction progress and sales data aren't available on K-RERA.
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
PLATINUM EAST WOODS
Complaints
0
on this project
PSR VANASREE PHASE-III
Complaints
0
on this project · 4 on M/s PSR BUILDERS AND DEVELOPERS overall
Builder track record
Across each promoter's other K-RERA registered projects
PLATINUM EAST WOODS
PLATINUM - NARYA INFRA
No other K-RERA registered projects on file for this promoter.
PSR VANASREE PHASE-III
M/s PSR BUILDERS AND DEVELOPERS
3 other projects on K-RERA · 1 delivered (100% complete) · avg 48.0% complete
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
PLATINUM EAST WOODS
No risk signals from filed quarters.
PSR VANASREE PHASE-III
Promoter pattern 1 of 3 other projects show the same delay-risk pattern
PLATINUM EAST WOODS — escrow account details
Bank
Bank of Baroda
Branch
J P Nagar 2nd Phase
IFSC
BARB0JPNAGA
70% Collection A/C
27500200002177
PSR VANASREE PHASE-III — escrow account details
Bank
Canara Bank
Branch
Hebbal Branch
IFSC
CNRB0000425
70% Collection A/C
120036880219
100% A/C
120036880412
30% A/C
2673214000029
PLATINUM EAST WOODS — details
Total units
188
Total cost
₹128.68 Cr
Project start
2023-03-08
Proposed completion
2027-03-30
Address
SY 191, , Kannamangala Village ,Bidarahalli Hobli , Bengaluru East , Bengaluru Urban, Karnataka - 560067
PSR VANASREE PHASE-III — details
Total units
168
Total cost
₹124.12 Cr
Project start
2026-03-01
Proposed completion
2028-12-31
Address
SY 81, KODATHI VILLAGE , VARTHURU HOBLI , Bengaluru East , Bengaluru Urban, Karnataka - 560035