Compare / Aslam Enclave vs SOGADU VILLAGE

Aslam Enclave vs SOGADU VILLAGE

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
Aslam Enclave
Tumakuru · Tumakuru
Delivered · 100% built
Mohammed Aslam PRM/KA/RERA/1272/394/PR/310725/007966
SOGADU VILLAGE
Tumakuru · Tumakuru
Active
S SHIVANNA AND S NAGARATHNA PRM/KA/RERA/1272/394/PR/100926/008928
Aslam Enclave
Construction
100%
as of Q4 2025-26
Sold
—
of ? · +0 last qtr
Available
0
SOGADU VILLAGE
No quarterly filings found for SOGADU VILLAGE yet — construction progress and sales data aren't available on K-RERA.
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Aslam Enclave
Complaints
0
on this project
SOGADU VILLAGE
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
Aslam Enclave
Mohammed Aslam
No other K-RERA registered projects on file for this promoter.
SOGADU VILLAGE
S SHIVANNA AND S NAGARATHNA
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Aslam Enclave
No risk signals from filed quarters.
SOGADU VILLAGE
No risk signals from filed quarters.
Aslam Enclave — escrow account details
Bank
Industrial Development Bank of India
Branch
TUMKUR
IFSC
IBKL000036
70% Collection A/C
0362102000013095
100% A/C
0362102000013101
30% A/C
0362102000013086
SOGADU VILLAGE — escrow account details
Bank
FEDERAL BANK OF INDIA
Branch
TUMKUR
IFSC
FDRL0001603
70% Collection A/C
16030200008208
100% A/C
16030200008216
30% A/C
16030200008190
Aslam Enclave — details
Total cost
₹5.08 Cr
Project start
2022-01-15
Proposed completion
2026-03-31
Address
Survey No. 22/6, measuring 0 acre 30 guntas situated Veerasagara Village, Kasaba hobli , Tumkur taluk, Tumkur district , situated Veerasagara Village, Kasaba hobli , Tumakur taluk, Tumakur district , Tumakuru , Tumakuru, Karnataka - 572225
SOGADU VILLAGE — details
Total cost
₹4.70 Cr
Project start
2025-06-27
Proposed completion
2029-12-31
Address
SY NO 9/3,4,5,6,7,10 AT RANGAPURA VILLAGE, , KASABA HOBLI, , Tumakuru , Tumakuru, Karnataka - 572201