Compare / Provident Ecopolitan Phase 5 vs SWARNA GRIHA VISTARA

Provident Ecopolitan Phase 5 vs SWARNA GRIHA VISTARA

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 9% built
PROVIDENT WHITE OAKS LLP PRM/KA/RERA/1251/309/PR/311224/007334
SWARNA GRIHA VISTARA
Dharwad · Bengaluru East
No quarterly filings
FELICITY ADOBE LLP PRM/KA/RERA/1259/410/PR/111126/009096
Provident Ecopolitan Phase 5
Construction
9%
as of Q1 2026-27
Sold
572
of 581 · +0 last qtr
Available
9
SWARNA GRIHA VISTARA
No quarterly filings found for SWARNA GRIHA VISTARA yet — construction progress and sales data aren't available on K-RERA.
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Provident Ecopolitan Phase 5
Complaints
0
on this project · 2 on PROVIDENT WHITE OAKS LLP overall
SWARNA GRIHA VISTARA
Complaints
0
on this project · 6 on FELICITY ADOBE LLP overall
Builder track record
Across each promoter's other K-RERA registered projects
Provident Ecopolitan Phase 5
PROVIDENT WHITE OAKS LLP
No other K-RERA registered projects on file for this promoter.
SWARNA GRIHA VISTARA
FELICITY ADOBE LLP
3 other projects on K-RERA · 1 delivered (100% complete) · avg 90.3% complete
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Provident Ecopolitan Phase 5
Escrow 1 quarter(s) withdrawn with no matching progress
SWARNA GRIHA VISTARA
No risk signals from filed quarters.
Provident Ecopolitan Phase 5 — escrow account details
Bank
HDFC
Branch
Ulsoor Road Branch
IFSC
HDFC0003689
70% Collection A/C
99981473577380
100% A/C
99998147357738
30% A/C
99999920240011
SWARNA GRIHA VISTARA — escrow account details
Bank
Canara Bank
Branch
Trinity Circle
IFSC
CNRR000792
70% Collection A/C
120041824062
100% A/C
120041780161
30% A/C
120041679686
Provident Ecopolitan Phase 5 — details
Total units
581
Total cost
₹206.03 Cr
Project start
2025-01-15
Proposed completion
2029-04-30
Address
Hardware Park
SWARNA GRIHA VISTARA — details
Total units
674
Total cost
₹117.10 Cr
Project start
2026-09-30
Proposed completion
2030-09-30
Address
Sy no : 71/1, 71/2, 71/3, 71/4, 71/5 State Highway 96 , Nadupalli village, Hutlur Hobli, Honnenahalli Gram Panchayat Kolar, Karnataka , Kolar