Compare / Sobha Windsor Phase 4 Wing 9, 10 and 11 vs Sobha Arena the Plaza

Sobha Windsor Phase 4 Wing 9, 10 and 11 vs Sobha Arena the Plaza

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
0 complaints · 89% built
SOBHA LIMITED PRM/KA/RERA/1251/308/PR/270922/005267
0 complaints · 43% built
SOBHA LIMITED PRM/KA/RERA/1251/308/PR/270922/005269
Sobha Windsor Phase 4 Wing 9, 10 and 11
Construction
89%
as of Q1 2026-27
Sold
99
of 99 · +0 last qtr
Available
0
Sobha Arena the Plaza
Construction
43%
as of Q1 2026-27
Sold
99
of 99 · +0 last qtr
Available
0
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Sobha Windsor Phase 4 Wing 9, 10 and 11
Complaints
0
on this project · 222 on SOBHA LIMITED overall
Sobha Arena the Plaza
Complaints
0
on this project · 222 on SOBHA LIMITED overall
Builder track record
Across each promoter's other K-RERA registered projects
Sobha Windsor Phase 4 Wing 9, 10 and 11
SOBHA LIMITED
36 other projects on K-RERA · 8 delivered (100% complete) · avg 51.3% complete · 55 complaints across those projects
Sobha Arena the Plaza
SOBHA LIMITED
36 other projects on K-RERA · 8 delivered (100% complete) · avg 52.7% complete · 55 complaints across those projects
Sobha Windsor Phase 4 Wing 9, 10 and 11 — escrow account details
Bank
ICICI Bank
Branch
ICICI Towers, 1 Commissariat Road,,Bangalore
IFSC
ICIC0000002
70% Collection A/C
777705222295
Sobha Arena the Plaza — escrow account details
Bank
ICICI Bank
Branch
ICICI Towers, 1 Commissariat Road,,Bangalore
IFSC
ICIC0000002
70% Collection A/C
777705222895
Sobha Windsor Phase 4 Wing 9, 10 and 11 — details
Total units
99
Total cost
₹136.59 Cr
Project start
2023-04-01
Proposed completion
2027-12-31
Address
Sy No. 107(P), 115/2, 115/3, 115/4, 115/5, 116/3 situated at Nagondanahalli village and Sy No. 30/1, 30/6, Situated at Hagadur Village, K.R.Puram Hobli
Sobha Arena the Plaza — details
Total units
99
Total cost
₹154.77 Cr
Project start
2024-10-01
Proposed completion
2029-06-30
Address
Kanakapura Road, Bangalore