Compare / Amantran Anant Vihar vs GOURINANDAN ARCADE

Amantran Anant Vihar vs GOURINANDAN ARCADE

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
No quarterly filings
A S Developers PRM/KA/RERA/1249/447/PR/260722/005103
On track · 77% built
GOURINANDAN BUILDCON PRM/KA/RERA/1249/447/PR/290425/007697
Amantran Anant Vihar
No quarterly filings found for Amantran Anant Vihar yet — construction progress and sales data aren't available on K-RERA.
GOURINANDAN ARCADE
Construction
77%
as of Q1 2026-27
Sold
4
of 20 · +0 last qtr
Available
16
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Amantran Anant Vihar
Complaints
0
on this project
GOURINANDAN ARCADE
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
Amantran Anant Vihar
A S Developers
1 other project on K-RERA · 0 delivered (100% complete) · avg 65.0% complete
GOURINANDAN ARCADE
GOURINANDAN BUILDCON
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Amantran Anant Vihar
No risk signals from filed quarters.
GOURINANDAN ARCADE
No risk signals from filed quarters.
Amantran Anant Vihar — escrow account details
Bank
Union Bank of India
Branch
Hindwadi
IFSC
UBIN0545180
70% Collection A/C
451801010035408
GOURINANDAN ARCADE — escrow account details
Bank
The Cosmos Co-operative Bank Ltd.
Branch
TILAKWADI
IFSC
COSB000091
70% Collection A/C
091100106439
100% A/C
091100106446
30% A/C
091100106422
Amantran Anant Vihar — details
Total units
25
Total cost
₹9.27 Cr
Project start
2021-04-01
Proposed completion
2024-03-31 overdue
Address
CTS No- 2388 Bharat Nagar
GOURINANDAN ARCADE — details
Total units
20
Total cost
₹9.56 Cr
Project start
2025-01-15
Proposed completion
2029-07-20
Address