Compare / THE SANCTUARY PHASE III vs RRL NATURE WOODS

THE SANCTUARY PHASE III vs RRL NATURE WOODS

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
1 complaint
CLASSIC FEATHERLITE WATERFRONT DEVELOPERS LLP PRM/KA/RERA/1251/308/PR/120522/004880
Delivered · 100% built
RRL BUILDERS AND DEVELOPERS PRIVATE LIMITED PRM/KA/RERA/1251/308/PR/220424/006827
THE SANCTUARY PHASE III
No quarterly filings found for THE SANCTUARY PHASE III yet — construction progress and sales data aren't available on K-RERA.
RRL NATURE WOODS
Construction
100%
as of Q1 2026-27
Sold
75
of 103 · +6 last qtr
Available
28
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
THE SANCTUARY PHASE III
Complaints
1
on this project · 1 on CLASSIC FEATHERLITE WATERFRONT DEVELOPERS LLP overall
RRL NATURE WOODS
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
THE SANCTUARY PHASE III
CLASSIC FEATHERLITE WATERFRONT DEVELOPERS LLP
1 other project on K-RERA
RRL NATURE WOODS
RRL BUILDERS AND DEVELOPERS PRIVATE LIMITED
2 other projects on K-RERA · 0 delivered (100% complete) · avg 32.0% complete
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
THE SANCTUARY PHASE III
No risk signals from filed quarters.
RRL NATURE WOODS
No risk signals from filed quarters.
THE SANCTUARY PHASE III — escrow account details
Bank
ICICI Bank
Branch
Jeevan Bima Nagar
IFSC
ICIC0001420
70% Collection A/C
142005002932
RRL NATURE WOODS — escrow account details
Bank
AU Small Finance Bank
Branch
HSR LAYOUT
IFSC
AUBL0002556
70% Collection A/C
2302255651345924
100% A/C
2402255657866491
30% A/C
2302255651197121
THE SANCTUARY PHASE III — details
Total cost
₹39.12 Cr
Project start
2021-11-06
Proposed completion
2023-11-06 overdue
Address
Sy no: 1/6, 1/8, 1/10, 1/11, 2/1, 2/2, 2/3, 2/4, 2/5, 2/6, 2/7, 2/9, 2/10, 2/11, 24/2, 24/3, 24/4, 24/5, 25/1A, 25/1B, 25/2, 25/3, 26/1, 26/2, , 26/3, 26/4, 26/5, 27/1, 27/2, 32/2, 32/3, 33/1 , Anekal , Bengaluru Urban, Karnataka - 562125
RRL NATURE WOODS — details
Total units
103
Total cost
₹39.32 Cr
Project start
2024-04-15
Proposed completion
2026-12-31
Address
Survey No.151/3, 151/5 and 151/6 , E-Khatha No – 150200102200124471,Thindlu Village, Sarjapura Hobli,Anekal Taluk.