THE SANCTUARY PHASE III vs The District

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
1 complaint
CLASSIC FEATHERLITE WATERFRONT DEVELOPERS LLP PRM/KA/RERA/1251/308/PR/120522/004880
On track · 48% built
Naville Estates LLP PRM/KA/RERA/1251/308/PR/250825/008029
THE SANCTUARY PHASE III
No quarterly filings found for THE SANCTUARY PHASE III yet — construction progress and sales data aren't available on K-RERA.
The District
Construction
48%
as of Q1 2026-27
Sold
of ? · +0 last qtr
Available
0
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
THE SANCTUARY PHASE III
Complaints
1
on this project · 1 on CLASSIC FEATHERLITE WATERFRONT DEVELOPERS LLP overall
The District
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
THE SANCTUARY PHASE III
CLASSIC FEATHERLITE WATERFRONT DEVELOPERS LLP
1 other project on K-RERA
The District
Naville Estates LLP
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
THE SANCTUARY PHASE III
No risk signals from filed quarters.
The District
Delay risk trending ~4 month(s) past declared completion
THE SANCTUARY PHASE III — escrow account details
Bank
ICICI Bank
Branch
Jeevan Bima Nagar
IFSC
ICIC0001420
70% Collection A/C
142005002932
The District — escrow account details
Bank
INDUSIND BANK
Branch
Whitefield Branch
IFSC
INDB0000894
70% Collection A/C
2597415000147
100% A/C
259916147779
30% A/C
259916147778
THE SANCTUARY PHASE III — details
Total cost
₹39.12 Cr
Project start
2021-11-06
Proposed completion
2023-11-06 overdue
Address
Sy no: 1/6, 1/8, 1/10, 1/11, 2/1, 2/2, 2/3, 2/4, 2/5, 2/6, 2/7, 2/9, 2/10, 2/11, 24/2, 24/3, 24/4, 24/5, 25/1A, 25/1B, 25/2, 25/3, 26/1, 26/2, , 26/3, 26/4, 26/5, 27/1, 27/2, 32/2, 32/3, 33/1 , Anekal , Bengaluru Urban, Karnataka - 562125
The District — details
Total cost
₹39.89 Cr
Project start
2025-08-01
Proposed completion
2026-11-30
Address
Sy No 32/8, 33, 34, 36, 39/2, 39/4, 39/5 & 39/6 of Nosennuru Golahalli Village, , Jigani Hobli, Anekal Taluk, Bangalore Urban District , Anekal , Bengaluru Urban, Karnataka - 562106