Compare / BEML 3RD STAGE ANNEXUE 4 vs Kuberanandhasagara Layout Phase 4

BEML 3RD STAGE ANNEXUE 4 vs Kuberanandhasagara Layout Phase 4

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
Delivered · 100% built
ESS AND ESS INFRASTRUCTURE PRIVATE LIMITED PRM/KA/RERA/1268/378/PR/110625/007813
BEML 3RD STAGE ANNEXUE 4
No quarterly filings found for BEML 3RD STAGE ANNEXUE 4 yet — construction progress and sales data aren't available on K-RERA.
Kuberanandhasagara Layout Phase 4
Construction
100%
as of Q1 2026-27
Sold
of ? · +0 last qtr
Available
0
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
BEML 3RD STAGE ANNEXUE 4
Complaints
0
on this project
Kuberanandhasagara Layout Phase 4
Complaints
0
on this project · 6 on ESS AND ESS INFRASTRUCTURE PRIVATE LIMITED overall
Builder track record
Across each promoter's other K-RERA registered projects
BEML 3RD STAGE ANNEXUE 4
BEMLEMPLOYEES HOUSE BUILDING CO OPERATIVE SOCIETY LTD MYSORE
1 other project on K-RERA · 0 delivered (100% complete) · avg 80.0% complete
Kuberanandhasagara Layout Phase 4
ESS AND ESS INFRASTRUCTURE PRIVATE LIMITED
14 other projects on K-RERA · 4 delivered (100% complete) · avg 99.3% complete
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
BEML 3RD STAGE ANNEXUE 4
No risk signals from filed quarters.
Kuberanandhasagara Layout Phase 4
Promoter pattern 2 of 8 other projects show the same delay-risk pattern
BEML 3RD STAGE ANNEXUE 4 — escrow account details
Bank
Axis Bank
Branch
MYSORE
IFSC
UTIB0000151
70% Collection A/C
922020005558666
Kuberanandhasagara Layout Phase 4 — escrow account details
Bank
Union Bank of India
Branch
Ramakrishnanagar
IFSC
UBIN0918598
70% Collection A/C
185921010000188
100% A/C
185921010000179
30% A/C
185921010000187
BEML 3RD STAGE ANNEXUE 4 — details
Total cost
₹4.40 Cr
Project start
2022-02-09
Proposed completion
2024-05-24 overdue
Address
SY NO-228/2A, 240/2, 240/4, 241/1, 241/3, 265/2, 266/2, 266/20 , 3RD STG MANDAKALLI Village, , MYSORE , Mysore, Karnataka - 500000
Kuberanandhasagara Layout Phase 4 — details
Total cost
₹4.76 Cr
Project start
2025-04-10
Proposed completion
2030-05-20
Address
Maidhanahalli Village, Ilwala Hobli, Mysore Taluk, Mysore District.