Compare / REB GRAND VIEW vs LUCENT

REB GRAND VIEW vs LUCENT

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 49% built
RAI ESTATES AND BUILDERS PRIVATE LIMITED PRM/KA/RERA/1257/334/PR/140622/004979
LUCENT
Dakshina Kannada · Mangalore
On track · 55% built
M/s MOHTISHAM COMPLEXES PVT LTD PRM/KA/RERA/1257/334/PR/101023/006310
REB GRAND VIEW
Construction
49%
as of Q1 2026-27
Sold
50
of 201 · +2 last qtr
Available
151
LUCENT
Construction
55%
as of Q1 2026-27
Sold
54
of 130 · +2 last qtr
Available
76
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
REB GRAND VIEW
Complaints
0
on this project
LUCENT
Complaints
0
on this project · 1 on M/s MOHTISHAM COMPLEXES PVT LTD overall
Builder track record
Across each promoter's other K-RERA registered projects
REB GRAND VIEW
RAI ESTATES AND BUILDERS PRIVATE LIMITED
No other K-RERA registered projects on file for this promoter.
LUCENT
M/s MOHTISHAM COMPLEXES PVT LTD
1 other project on K-RERA · 0 delivered (100% complete) · avg 74.0% complete
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
REB GRAND VIEW
Delay risk trending ~9 month(s) past declared completion
LUCENT
Delay risk construction progress far too slow to plausibly hit declared completion
Promoter pattern 1 of 1 other projects show the same delay-risk pattern
REB GRAND VIEW — escrow account details
Bank
Bank of Baroda
Branch
Bejai
IFSC
BARB0VJBIJA
70% Collection A/C
74130200001437
LUCENT — escrow account details
Bank
STATE BANK OF INDIA
Branch
SME BRANCH
IFSC
SBIN4118
70% Collection A/C
42342847637
100% A/C
42342838270
30% A/C
42310513644
REB GRAND VIEW — details
Total units
201
Total cost
₹66.21 Cr
Project start
2022-06-05
Proposed completion
2029-12-31
Address
By pass Road.Puttur,D.k
LUCENT — details
Total units
130
Total cost
₹49.50 Cr
Project start
2023-08-15
Proposed completion
2027-07-30
Address
ATTAVAR, MANGALORE