Compare / COLOSSAL ROSE MALLOW vs SRI SAI NANDANA CRYSTAL

COLOSSAL ROSE MALLOW vs SRI SAI NANDANA CRYSTAL

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
No quarterly filings
COLOSSAL DEVELOPERS PRIVATE LIMITED PRM/KA/RERA/1251/308/PR/031022/005293
On track · 56% built
SRI SAI NANDANA BUILDERS PRM/KA/RERA/1251/308/PR/220825/008023
COLOSSAL ROSE MALLOW
No quarterly filings found for COLOSSAL ROSE MALLOW yet — construction progress and sales data aren't available on K-RERA.
SRI SAI NANDANA CRYSTAL
Construction
56%
as of Q1 2026-27
Sold
16
of 44 · +9 last qtr
Available
28
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
COLOSSAL ROSE MALLOW
Complaints
0
on this project
SRI SAI NANDANA CRYSTAL
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
COLOSSAL ROSE MALLOW
COLOSSAL DEVELOPERS PRIVATE LIMITED
No other K-RERA registered projects on file for this promoter.
SRI SAI NANDANA CRYSTAL
SRI SAI NANDANA BUILDERS
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
COLOSSAL ROSE MALLOW
No risk signals from filed quarters.
SRI SAI NANDANA CRYSTAL
No risk signals from filed quarters.
COLOSSAL ROSE MALLOW — escrow account details
Bank
HDFC
Branch
MARATHAHALLI
IFSC
HDFC0001300
70% Collection A/C
50200066895833
SRI SAI NANDANA CRYSTAL — escrow account details
Bank
FEDERAL BANK OF INDIA
Branch
Banglore/ Banashankari
IFSC
FDRL0001781
70% Collection A/C
17810200005695
100% A/C
17810200005679
30% A/C
17810200005687
COLOSSAL ROSE MALLOW — details
Total units
35
Total cost
₹36.88 Cr
Project start
2022-06-15
Proposed completion
2024-12-25 overdue
Address
PROPERTY NO 150200100200321620, VILLAGE PANCHAYAT NO 2048/81/2 , SY NO 81/1, 81/2, 81/3P, INDLABELE VILLAGE , Anekal , Bengaluru Urban, Karnataka - 562107
SRI SAI NANDANA CRYSTAL — details
Total units
44
Total cost
₹34.39 Cr
Project start
2025-07-30
Proposed completion
2030-12-31
Address
Situated at Sy no 85/4 , Property No.2873/85/4 ,E Khatha No. 150200100100223720 , Chambenahalli Village , Sarjapura Hobli , Anekal , Bengaluru Urban, Karnataka - 562125