AFTER THE RAIN-PHASE IIC vs LEGACY MAXIMUS
Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
AFTER THE RAIN-PHASE IIC
Bengaluru Urban · Bengaluru North
On track · 48% built
Total Environment Building Systems Private limited
PRM/KA/RERA/1251/309/PR/300322/004795
LEGACY MAXIMUS
Bengaluru Urban · Bengaluru North
On track · 48% built
LEGACY GLOBAL PROJECTS PVT LTD
PRM/KA/RERA/1251/309/PR/310125/007465
AFTER THE RAIN-PHASE IIC
Construction
48%
as of Q1 2026-27
Sold
24
of 26
· +0 last qtr
Available
2
LEGACY MAXIMUS
Construction
48%
as of Q1 2026-27
Sold
6
of 12
· +0 last qtr
Available
7
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
AFTER THE RAIN-PHASE IIC
Complaints
0
on this project · 3 on Total Environment Building Systems Private limited overall
LEGACY MAXIMUS
Complaints
0
on this project · 18 on LEGACY GLOBAL PROJECTS PVT LTD overall
Builder track record
Across each promoter's other K-RERA registered projects
AFTER THE RAIN-PHASE IIC
Total Environment Building Systems Private limited
No other K-RERA registered projects on file for this promoter.
LEGACY MAXIMUS
LEGACY GLOBAL PROJECTS PVT LTD
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
AFTER THE RAIN-PHASE IIC
Delay risk
no completion progress across filed quarters
Escrow
2 quarter(s) withdrawn with no matching progress
LEGACY MAXIMUS
Delay risk
construction progress far too slow to plausibly hit declared completion
AFTER THE RAIN-PHASE IIC — escrow account details
LEGACY MAXIMUS — escrow account details
AFTER THE RAIN-PHASE IIC — details
LEGACY MAXIMUS — details