AFTER THE RAIN-PHASE IIC vs Magnolia Delight
Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
AFTER THE RAIN-PHASE IIC
Bengaluru Urban · Bengaluru North
On track · 48% built
Total Environment Building Systems Private limited
PRM/KA/RERA/1251/309/PR/300322/004795
Magnolia Delight
Bengaluru Urban · Bengaluru North
On track · 35% built
Magnolia Infrastructure Development Limited
PRM/KA/RERA/1251/309/PR/230525/007772
AFTER THE RAIN-PHASE IIC
Construction
48%
as of Q1 2026-27
Sold
24
of 26
· +0 last qtr
Available
2
Magnolia Delight
Construction
35%
as of Q1 2026-27
Sold
7
of 48
· +1 last qtr
Available
41
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
AFTER THE RAIN-PHASE IIC
Complaints
0
on this project · 3 on Total Environment Building Systems Private limited overall
Magnolia Delight
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
AFTER THE RAIN-PHASE IIC
Total Environment Building Systems Private limited
No other K-RERA registered projects on file for this promoter.
Magnolia Delight
Magnolia Infrastructure Development Limited
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
AFTER THE RAIN-PHASE IIC
Delay risk
no completion progress across filed quarters
Escrow
2 quarter(s) withdrawn with no matching progress
Magnolia Delight
Delay risk
trending ~5 month(s) past declared completion
AFTER THE RAIN-PHASE IIC — escrow account details
Magnolia Delight — escrow account details
AFTER THE RAIN-PHASE IIC — details
Magnolia Delight — details