Compare / Meridian Park Phase III @ The Prestige City vs Adarsh Welkin Park Phase 1

Meridian Park Phase III @ The Prestige City vs Adarsh Welkin Park Phase 1

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
On track · 91% built
PRESTIGE PROJECTS PRIVATE LIMITED PRM/KA/RERA/1251/308/PR/110822/005151
1 complaint · 78% built
Akarshak Realty Private Limited PRM/KA/RERA/1251/308/PR/020923/006223
Meridian Park Phase III @ The Prestige City
Construction
91%
as of Q1 2026-27
Sold
898
of 898 · +0 last qtr
Available
0
Adarsh Welkin Park Phase 1
Construction
78%
as of Q1 2026-27
Sold
812
of 832 · +0 last qtr
Available
20
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
Meridian Park Phase III @ The Prestige City
Complaints
0
on this project · 11 on PRESTIGE PROJECTS PRIVATE LIMITED overall
Adarsh Welkin Park Phase 1
Complaints
1
on this project · 5 on Akarshak Realty Private Limited overall
Builder track record
Across each promoter's other K-RERA registered projects
Meridian Park Phase III @ The Prestige City
PRESTIGE PROJECTS PRIVATE LIMITED
7 other projects on K-RERA · 1 delivered (100% complete) · avg 57.5% complete · 5 complaints across those projects
Adarsh Welkin Park Phase 1
Akarshak Realty Private Limited
2 other projects on K-RERA · 0 delivered (100% complete) · avg 14.0% complete · 1 complaint across those projects
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
Meridian Park Phase III @ The Prestige City
Delay risk no completion progress across filed quarters
Escrow 1 quarter(s) withdrawn with no matching progress
Promoter pattern 3 of 6 other projects show the same delay-risk pattern
Adarsh Welkin Park Phase 1
Promoter pattern 1 of 2 other projects show the same delay-risk pattern
Meridian Park Phase III @ The Prestige City — escrow account details
Bank
KOTAK MAHINDRA BANK
Branch
Lavelle Road
IFSC
KKBK0000422
70% Collection A/C
7745095810
Adarsh Welkin Park Phase 1 — escrow account details
Bank
ICICI Bank
Branch
Residency road Branch, Bangalore
IFSC
ICIC0007429
70% Collection A/C
777705007569
Meridian Park Phase III @ The Prestige City — details
Total units
898
Total cost
₹633.88 Cr
Project start
2022-11-01
Proposed completion
2026-08-27 overdue
Address
The Prestige City, near Yamare Panchayath Office, V.K.Halli and Ittangur Village, Sarjapura Hobli, Anekal Taluk,
Adarsh Welkin Park Phase 1 — details
Total units
832
Total cost
₹749.09 Cr
Project start
2023-07-01
Proposed completion
2027-12-31
Address
GATTIHALLI VILLAGE, SARJAPURA HOBLI, ANEKAL TALUK. BENGALURU