Compare / SINGHI COLONY vs JR GREENWICH PHASE III

SINGHI COLONY vs JR GREENWICH PHASE III

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
SINGHI COLONY
Ballari · Bengaluru East
Active
M/s. SNEH SHELTERS PRIVATE LIMITED PRM/KA/RERA/1248/469/PR/020922/005208
Delivered · 100% built
JR HOUSING DEVELOPERS PVT LTD PRM/KA/RERA/1251/308/PR/210524/006915
SINGHI COLONY
No quarterly filings found for SINGHI COLONY yet — construction progress and sales data aren't available on K-RERA.
JR GREENWICH PHASE III
Construction
100%
as of Q3 2025-26
Sold
of ? · +0 last qtr
Available
0
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
SINGHI COLONY
Complaints
0
on this project
JR GREENWICH PHASE III
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
SINGHI COLONY
M/s. SNEH SHELTERS PRIVATE LIMITED
No other K-RERA registered projects on file for this promoter.
JR GREENWICH PHASE III
JR HOUSING DEVELOPERS PVT LTD
1 other project on K-RERA
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
SINGHI COLONY
No risk signals from filed quarters.
JR GREENWICH PHASE III
No risk signals from filed quarters.
SINGHI COLONY — escrow account details
Bank
Axis Bank
Branch
RICHMOND ROAD BANGALORE
IFSC
UTIB0003095
70% Collection A/C
922020015018585
JR GREENWICH PHASE III — escrow account details
Bank
Karnataka Bank Ltd.
Branch
NEHRUNAGAR
IFSC
KARB0000063
70% Collection A/C
1302000100102301
100% A/C
1302000100102201
30% A/C
1302000100102401
SINGHI COLONY — details
Total cost
₹6.20 Cr
Project start
2022-04-08
Proposed completion
2023-12-30 overdue
Address
TS NO 74/2, NEW TS NO. 74/2A/1a,CTS WARD NO.22, BLOCK NO.9, CMC Ward No.25, New Assement No.40183,40184,49783/A, CANTONMENT BALLARI , TS NO 74/2, NEW TS NO. 74/2A/1a,CTS WARD NO.22, BLOCK NO.9, CMC Ward No.25, New Assement No.40183,40184,49783/A, CANTONMENT BALLARI , Ballari , Ballari, Karnataka - 583103
JR GREENWICH PHASE III — details
Total cost
₹5.61 Cr
Project start
2023-12-30
Proposed completion
2028-11-20
Address
Next to Wipro Office, Kodathi Village, Varthuru Hobli, Bengaluru,