AMITY vs Kedar

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
AMITY
Dakshina Kannada · Dakshina Kannada
Delivered · 100% built
MOHTISHAM COMPLEXES PVT LTD PRM/KA/RERA/1257/334/PR/230522/004895
Kedar
Dakshina Kannada · Dakshina Kannada
On track · 92% built
Mukund MGM Realty PRM/KA/RERA/1257/333/PR/111022/005315
AMITY
Construction
100%
as of Q4 2025-26
Sold
88
of 107 · +0 last qtr
Available
19
Kedar
Construction
92%
as of Q1 2026-27
Sold
59
of 86 · +2 last qtr
Available
27
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
AMITY
Complaints
0
on this project · 1 on MOHTISHAM COMPLEXES PVT LTD overall
Kedar
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
AMITY
MOHTISHAM COMPLEXES PVT LTD
No other K-RERA registered projects on file for this promoter.
Kedar
Mukund MGM Realty
3 other projects on K-RERA · 1 delivered (100% complete) · avg 61.5% complete
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
AMITY
No risk signals from filed quarters.
Kedar
Promoter pattern 1 of 2 other projects show the same delay-risk pattern
AMITY — escrow account details
Bank
STATE BANK OF INDIA
Branch
SME BRANCH
IFSC
SBIN0004118
70% Collection A/C
40633122943
Kedar — escrow account details
Bank
INDIAN OVERSEAS BANK
Branch
Darebail
IFSC
IOBA0001769
70% Collection A/C
176902000002222
AMITY — details
Total units
107
Total cost
₹48.00 Cr
Project start
2021-12-01
Proposed completion
2026-02-28
Address
NANTOOR, MANGALORE
Kedar — details
Total units
86
Total cost
₹46.60 Cr
Project start
2022-09-01
Proposed completion
2027-08-31
Address
Sy No 79/2(P), 79/1(P) & 106/2A1(P), Derebail Village , Mangalore , Dakshina Kannada , Dakshina Kannada, Karnataka - 575006