Compare / KADRI ENCLAVE vs Anand Residnecy

KADRI ENCLAVE vs Anand Residnecy

Compliance and delivery signals from K-RERA quarterly filings — not price or amenities.
No quarterly filings
SHREE VIGNESHWARA DEVELOPERS PRM/KA/RERA/1257/334/PR/141022/005321
Delivered · 100% built
KAMALDEEP PROMOTERS & DEVELOPERS PRM/KA/RERA/1257/333/PR/120523/005927
KADRI ENCLAVE
No quarterly filings found for KADRI ENCLAVE yet — construction progress and sales data aren't available on K-RERA.
Anand Residnecy
Construction
100%
as of Q4 2025-26
Sold
31
of 42 · +4 last qtr
Available
11
Construction progress over time
% complete at each quarterly filing
Sales velocity over time
Units booked per quarterly filing
KADRI ENCLAVE
Complaints
0
on this project
Anand Residnecy
Complaints
0
on this project
Builder track record
Across each promoter's other K-RERA registered projects
KADRI ENCLAVE
SHREE VIGNESHWARA DEVELOPERS
2 other projects on K-RERA · 0 delivered (100% complete) · avg 63.0% complete
Anand Residnecy
KAMALDEEP PROMOTERS & DEVELOPERS
No other K-RERA registered projects on file for this promoter.
Risk signals
Computed from each promoter's own quarterly filings on K-RERA — an estimate, not a certified assessment
KADRI ENCLAVE
Promoter pattern 1 of 2 other projects show the same delay-risk pattern
Anand Residnecy
No risk signals from filed quarters.
KADRI ENCLAVE — escrow account details
Bank
Bank of Baroda
Branch
Bendoorwell
IFSC
BARB0VJBEND
70% Collection A/C
73650200001379
Anand Residnecy — escrow account details
Bank
STATE BANK OF INDIA
Branch
Mallikatta, Mangalore
IFSC
SBIN0003823
70% Collection A/C
41733777579
KADRI ENCLAVE — details
Total units
46
Total cost
₹11.36 Cr
Project start
2022-07-18
Proposed completion
2025-01-15 overdue
Address
Alvares Road Kadri Mangalore
Anand Residnecy — details
Total units
42
Total cost
₹10.44 Cr
Project start
2023-04-01
Proposed completion
2026-10-31
Address
Survey number 290-1(P), 290-1(P1), 290-1(2) of 79 Padav Village , Shakthinagar, Padav village, Shakthinagar, Mangalore