ELV KINGSLAND

Bengaluru Urban · ELV Projects Private Limited PRM/KA/RERA/1251/446/PR/181122/005469
6 complaints · 30% built
Filed — · Q1 2026-27
Construction
30%
complete
Sold
76
of 219 total units
Available
143
units
2 BHK: 119
2.5 BHK: 10
3 BHK: 14
Complaints
6
on project · 55 on builder
Construction progress
% complete per quarter
Sales velocity
Units sold per quarter · cumulative booked (line)
Inventory drain
Available units over time
Show financial data (advance collected vs withdrawn)
Quarterly financials
₹ Crore — advance collected vs amount withdrawn this quarter

Quarter-wise Tower Data

Filed: 2026-07-10 · Project 30% complete
ELV High Garden 30% complete
Unit type Total Booked Available
2 BHK 160 41 119
2.5 BHK 23 13 10
3 BHK 36 22 14
Parking 374 76 298
Floor completion
Floor 0
70.0%
Floor 1
60.0%
Floor 2
50.0%
Floor 3
30.0%
Floor 4
30.0%
Floor 5
20.0%
Floor 6
20.0%
Floor 7
20.0%
Floor 8
20.0%
Floor 9
0.0%
Floor 10
0.0%
Floor 11
0.0%
Floor 12
0.0%
Floor 13
0.0%

Unit Specifications

Unit type Carpet area (sqft) Units
2 BHK 9,020–9,418 320 Estimate ROI →
2.5 BHK 11,421–11,474 46 Estimate ROI →
3 BHK 12,755–13,756 72 Estimate ROI →
Show escrow account details
Escrow Accounts
Bank
RATNAKAR BANK
Branch
prestige towers
IFSC
RATN0000156
70% Collection A/C
409002398243
100% A/C
409002398250
30% A/C
409002398281

Project details

Registration no.
PRM/KA/RERA/1251/446/PR/181122/005469
District
Bengaluru Urban
Taluk
Bengaluru East
Promoter
ELV Projects Private Limited
Firm type
Company
PAN
AAECE1841N
GSTIN
29AAECE1841NIZC
Total units
219
Total cost
₹169.15 Cr
Project start
2022-10-02
FAR sanctioned
31869.0
Proposed completion
2026-10-02
Project address
#50/11, Borewell Road, Whitefield, Bangalore.

Complaint History 23 complaints

Complaint no. Filed Subject Status
CMP/221125/0010399 2022-11-25 Non commencing of the project as per the agreement and causing mental agony and financial loss to the complainant Disposed
CMP/221125/0010398 2022-11-25 Despite more than 4 years, the project is not Completed and undue delay in completion - deliberate inaction Disposed
CMP/221114/0010324 2022-11-14 Non commencing of the project as per the agreement and causing mental agony and financial loss to the complainant Disposed
CMP/221114/0010323 2022-11-14 Non commencing of the project as per the agreement and causing mental agony and financial loss to the complainant Disposed
CMP/221114/0010322 2022-11-14 Non commencing of the project as per the agreement and causing mental agony and financial loss to the complainant Disposed
CMP/221114/0010321 2022-11-14 Non commencing of the project as per the agreement and causing mental agony and financial loss to the complainant Disposed
CMP/221114/0010320 2022-11-14 Non commencing of the project as per the agreement and causing mental agony and financial loss to the complainant Disposed
CMP/221114/0010319 2022-11-14 Non commencing of the project as per the agreement and causing mental agony and financial loss to the complainant Disposed
CMP/221114/0010318 2022-11-14 Non commencing of the project as per the agreement and causing mental agony and financial loss to the complainant Disposed
CMP/221114/0010317 2022-11-14 Non commencing of the project as per the agreement and causing mental agony and financial loss to the complainant Disposed
CMP/221114/0010316 2022-11-14 Non commencing of the project as per the agreement and causing mental agony and financial loss to the complainant Disposed
CMP/221114/0010313 2022-11-14 Non commencing of the project as per the agreement and causing mental agony and financial loss to the complainant Disposed
CMP/221114/0010293 2022-11-14 Despite more than 4 years, the project is not Completed and undue delay in completion - deliberate inaction Disposed
CMP/221114/0010292 2022-11-14 Despite more than 4 years, the project is not Completed and undue delay in completion - deliberate inaction Disposed
CMP/221114/0010291 2022-11-14 Despite more than 4 years, the project is not Completed and undue delay in completion - deliberate inaction Disposed
CMP/221114/0010288 2022-11-14 Despite more than 4 years, the project is not Completed and undue delay in completion - deliberate inaction Disposed
CMP/221114/0010286 2022-11-14 Despite more than 4 years, the project is not Completed and undue delay in completion - deliberate inaction Disposed
CMP/221114/0010285 2022-11-14 Despite more than 4 years, the project is not Completed and undue delay in completion - deliberate inaction Disposed
CMP/221114/0010283 2022-11-14 Despite more than 4 years, the project is not Completed and undue delay in completion - deliberate inaction Disposed
CMP/221114/0010278 2022-11-14 Despite lapse of 57 months, project not delivered - deliberate inaction Disposed
CMP/221114/0010276 2022-11-14 Despite more than 4 years, the project is not undertaken- Deliberate inaction Disposed
CMP/221010/0010082 2022-10-10 Despite more than 4 years, the project is not undertaken- deliberate inaction Disposed
CMP/190611/0003276 2019-06-11 Revoking the REGISTRATION CERTIFICATE OF PROJECT (Company) dated 22.11.2018 bearing project registration No.PRM/KA/RARA/1251/ 446/PR/18122/002144 of project Disposed

Frequently Asked Questions

Based on K-RERA registered data for ELV KINGSLAND
Is ELV KINGSLAND RERA registered in Karnataka?

Yes. ELV KINGSLAND is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1251/446/PR/181122/005469.

What is the RERA registration number of ELV KINGSLAND?

The K-RERA registration number of ELV KINGSLAND is PRM/KA/RERA/1251/446/PR/181122/005469.

What is the current construction status of ELV KINGSLAND?

As of Q1 2026-27, ELV KINGSLAND is 30% complete according to its latest K-RERA quarterly filing.

Are flats still available in ELV KINGSLAND?

Yes. As per the latest K-RERA quarterly filing (Q1 2026-27), ELV KINGSLAND has 143 unit(s) available for purchase.

How many flats have been sold in ELV KINGSLAND?

As per the latest K-RERA filing (Q1 2026-27), 76 out of 219 units in ELV KINGSLAND have been sold or booked.

Are 2 BHK flats available in ELV KINGSLAND?

Yes. According to the latest K-RERA quarterly filing, there are 119 2 BHK unit(s) available in ELV KINGSLAND, Bengaluru Urban.

Are 2.5 BHK flats available in ELV KINGSLAND?

Yes. According to the latest K-RERA quarterly filing, there are 10 2.5 BHK unit(s) available in ELV KINGSLAND, Bengaluru Urban.

Are 3 BHK flats available in ELV KINGSLAND?

Yes. According to the latest K-RERA quarterly filing, there are 14 3 BHK unit(s) available in ELV KINGSLAND, Bengaluru Urban.

Are there any RERA complaints against ELV KINGSLAND?

Yes. ELV KINGSLAND has 6 complaint(s) filed against it on the K-RERA portal. Review these on the official K-RERA website before making a purchase decision.

How many RERA complaints does ELV Projects Private Limited have?

ELV Projects Private Limited, the builder/promoter of ELV KINGSLAND, has 55 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.

Who is the builder or developer of ELV KINGSLAND?

ELV KINGSLAND is developed by ELV Projects Private Limited, a company registered with K-RERA in Bengaluru Urban, Karnataka.

When did ELV KINGSLAND last file a quarterly update with K-RERA?

ELV KINGSLAND last filed a quarterly update for Q1 2026-27 on 2026-07-10. The project has submitted 3 quarterly report(s) on K-RERA to date.