Delivered · 100% built
Filed — · Q3 2025-26
Construction
100%
complete
Sold
of ? total units
Available
0
units
Complaints
1
on project · 2 on builder
Construction progress
% complete per quarter
Sales velocity
Units sold per quarter · cumulative booked (line)
Inventory drain
Available units over time
Show financial data (advance collected vs withdrawn)
Quarterly financials
₹ Crore — advance collected vs amount withdrawn this quarter

Quarter-wise Tower Data

Filed: 2026-01-14 · Project 100% complete

No tower breakdown recorded for this quarter.

Show escrow account details
Escrow Accounts
Bank
HDFC
Branch
Bilekahalli
IFSC
HDFC0001752
70% Collection A/C
99900029860210

Project details

Registration no.
PRM/KA/RERA/1265/347/PR/151222/005525
District
Kolar
Taluk
Bengaluru South
Promoter
Concorde Housing Corporation Pvt Ltd
Firm type
Company
PAN
AADCC4087F
GSTIN
29AADCC4087F1ZK
Total cost
₹50.04 Cr
Project start
2023-01-01
Land/property litigation
No
Proposed completion
2026-12-31
Project address
Sy No.5/1C & 7, Chikkasandra Village, Yeshwanthpura Hobli

Buyer Risk Report 1 complaint

1 risk signal detected · 1 complaint on file from this project's K-RERA quarterly filings.

Sign in free — no password — to see exactly which quarters and complaints triggered these flags.

Sign in to see full details →
Show documents on file with K-RERA (118)
Documents on file
Government NOCs
BESCOM (electricity) on file
BWSSB (water & sewerage) not found
Fire NOC not found
KSPCB (pollution control) on file
SEIAA (environmental clearance) not found
Airport / Air Force NOC not found
Telecom (BSNL) NOC not found
Lift license not found
RERA statutory forms
Form-1 (project registration) not found
Form-2/3 (CA certificate) not found
Form-B / Sec 3(1) affidavit not found
Company KYC
Certificate of incorporation not found
GST certificate not found
PAN card not found
Partnership deed / firm registration not found
Promoter financials
22 on file
Legal / land documents
14 on file
Other documents
36 on file · 11 marked not available
Plan approvals
6 on file
Sale/allotment documents
3 on file
Site photographs
4 on file
Technical certificates
6 on file
Inventory of documents the promoter has uploaded to their K-RERA project page — not a review of their contents. "Not found" means no filed document matched that item by name; it doesn't necessarily apply to every project (e.g. an airport-proximity NOC).

Frequently Asked Questions

Based on K-RERA registered data for Concorde Auriga
Is Concorde Auriga RERA registered in Karnataka?

Yes. Concorde Auriga is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1265/347/PR/151222/005525.

What is the RERA registration number of Concorde Auriga?

The K-RERA registration number of Concorde Auriga is PRM/KA/RERA/1265/347/PR/151222/005525.

What is the current construction status of Concorde Auriga?

As of Q3 2025-26, Concorde Auriga is 100% complete — construction has finished according to its latest K-RERA quarterly filing.

Are flats still available in Concorde Auriga?

As per the latest K-RERA filing (Q3 2025-26), Concorde Auriga is sold out — no units are currently listed as available.

Are there any RERA complaints against Concorde Auriga?

Yes. Concorde Auriga has 1 complaint(s) filed against it on the K-RERA portal. Review these on the official K-RERA website before making a purchase decision.

How many RERA complaints does Concorde Housing Corporation Pvt Ltd have?

Concorde Housing Corporation Pvt Ltd, the builder/promoter of Concorde Auriga, has 2 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.

Who is the builder or developer of Concorde Auriga?

Concorde Auriga is developed by Concorde Housing Corporation Pvt Ltd, a company registered with K-RERA in Kolar, Karnataka.

When did Concorde Auriga last file a quarterly update with K-RERA?

Concorde Auriga last filed a quarterly update for Q3 2025-26 on 2026-01-14. The project has submitted 1 quarterly report(s) on K-RERA to date.