Show documents on file with K-RERA (99)
| BESCOM (electricity) | on file |
| BWSSB (water & sewerage) | not found |
| Fire NOC | not found |
| KSPCB (pollution control) | on file |
| SEIAA (environmental clearance) | not found |
| Airport / Air Force NOC | not found |
| Telecom (BSNL) NOC | not found |
| Lift license | not found |
| Form-1 (project registration) | on file |
| Form-2/3 (CA certificate) | on file |
| Form-B / Sec 3(1) affidavit | on file |
| Certificate of incorporation | not found |
| GST certificate | not found |
| PAN card | on file |
| Partnership deed / firm registration | not found |
Frequently Asked Questions
Is AVANI ABODE RERA registered in Karnataka?
Yes. AVANI ABODE is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1251/446/PR/220223/005736.
What is the RERA registration number of AVANI ABODE?
The K-RERA registration number of AVANI ABODE is PRM/KA/RERA/1251/446/PR/220223/005736.
What is the current construction status of AVANI ABODE?
As of Q1 2026-27, AVANI ABODE is 99% complete according to its latest K-RERA quarterly filing.
Are flats still available in AVANI ABODE?
As per the latest K-RERA filing (Q1 2026-27), AVANI ABODE is sold out — no units are currently listed as available.
Are there any RERA complaints against AVANI ABODE?
As per K-RERA data tracked by rera.watch, there are no complaints currently recorded against AVANI ABODE.
How many RERA complaints does N G DEVELOPERS have?
N G DEVELOPERS, the builder/promoter of AVANI ABODE, has 0 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.
Who is the builder or developer of AVANI ABODE?
AVANI ABODE is developed by N G DEVELOPERS, a partnership firm registered with K-RERA in Bengaluru Urban, Karnataka.
When did AVANI ABODE last file a quarterly update with K-RERA?
AVANI ABODE last filed a quarterly update for Q1 2026-27 on 2026-07-15. The project has submitted 3 quarterly report(s) on K-RERA to date.