Sobha Neopolis Phase 1 - W 14, 15, 16, 17, 18 &19
Show financial data (advance collected vs withdrawn)
Quarter-wise Tower Data
Wing 14 100% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 1 BHK | 111 | 111 | 0 |
| Parking | 56 | 56 | — |
Wing 15 100% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 1 BHK | 114 | 113 | 1 |
| Parking | 57 | 57 | — |
Wing 16 100% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 3 BHK | 112 | 111 | 1 |
| Parking | 112 | 111 | 1 |
Wing 17 100% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 3 BHK | 112 | 112 | 0 |
| Parking | 112 | 112 | — |
Wing 18 100% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 4 BHK | 75 | 66 | 9 |
| Parking | 75 | 73 | 2 |
Wing 19 100% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 4 BHK | 76 | 57 | 19 |
| Parking | 76 | 65 | 11 |
Wing 14 100% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 1 BHK | 111 | 111 | 0 |
| 1 BHK | 111 | 111 | 0 |
| 1 BHK | 111 | 111 | 0 |
| 1 BHK | 111 | 111 | 0 |
| Parking | 56 | 56 | — |
Wing 15 100% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 1 BHK | 114 | 114 | 0 |
| 1 BHK | 114 | 114 | 0 |
| 1 BHK | 114 | 114 | 0 |
| 1 BHK | 114 | 114 | 0 |
| Parking | 57 | 57 | — |
Wing 16 100% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 3 BHK | 112 | 110 | 2 |
| 3 BHK | 112 | 110 | 2 |
| 3 BHK | 112 | 110 | 2 |
| 3 BHK | 112 | 110 | 2 |
| Parking | 112 | 111 | 1 |
Wing 17 100% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 3 BHK | 112 | 112 | 0 |
| 3 BHK | 112 | 112 | 0 |
| 3 BHK | 112 | 112 | 0 |
| 3 BHK | 112 | 112 | 0 |
| Parking | 112 | 112 | — |
Wing 18 100% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 4 BHK | 75 | 59 | 16 |
| 4 BHK | 75 | 59 | 16 |
| 4 BHK | 75 | 59 | 16 |
| 4 BHK | 75 | 59 | 16 |
| Parking | 75 | 74 | 1 |
Wing 19 100% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 4 BHK | 76 | 50 | 26 |
| 4 BHK | 76 | 50 | 26 |
| 4 BHK | 76 | 50 | 26 |
| 4 BHK | 76 | 50 | 26 |
| Parking | 76 | 64 | 12 |
Wing 14 100% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 1 BHK | 111 | 111 | 0 |
| 1 BHK | 111 | 111 | 0 |
| 1 BHK | 111 | 111 | 0 |
| 1 BHK | 111 | 111 | 0 |
| 1 BHK | 111 | 111 | 0 |
| 1 BHK | 111 | 111 | 0 |
| 1 BHK | 111 | 111 | 0 |
| 1 BHK | 111 | 111 | 0 |
| Parking | 56 | 56 | — |
Wing 15 100% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 1 BHK | 114 | 114 | 0 |
| 1 BHK | 114 | 114 | 0 |
| 1 BHK | 114 | 114 | 0 |
| 1 BHK | 114 | 114 | 0 |
| 1 BHK | 114 | 114 | 0 |
| 1 BHK | 114 | 114 | 0 |
| 1 BHK | 114 | 114 | 0 |
| 1 BHK | 114 | 114 | 0 |
| Parking | 57 | 57 | — |
Wing 16 100% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 3 BHK | 112 | 110 | 2 |
| 3 BHK | 112 | 110 | 2 |
| 3 BHK | 112 | 110 | 2 |
| 3 BHK | 112 | 110 | 2 |
| 3 BHK | 112 | 110 | 2 |
| 3 BHK | 112 | 110 | 2 |
| 3 BHK | 112 | 110 | 2 |
| 3 BHK | 112 | 110 | 2 |
| Parking | 112 | 111 | 1 |
Wing 17 100% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 3 BHK | 112 | 108 | 4 |
| 3 BHK | 112 | 108 | 4 |
| 3 BHK | 112 | 108 | 4 |
| 3 BHK | 112 | 108 | 4 |
| 3 BHK | 112 | 108 | 4 |
| 3 BHK | 112 | 108 | 4 |
| 3 BHK | 112 | 108 | 4 |
| 3 BHK | 112 | 108 | 4 |
| Parking | 112 | 109 | 3 |
Wing 18 100% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 4 BHK | 75 | 59 | 16 |
| 4 BHK | 75 | 59 | 16 |
| 4 BHK | 75 | 59 | 16 |
| 4 BHK | 75 | 59 | 16 |
| 4 BHK | 75 | 59 | 16 |
| 4 BHK | 75 | 59 | 16 |
| 4 BHK | 75 | 59 | 16 |
| 4 BHK | 75 | 59 | 16 |
| Parking | 75 | 73 | 2 |
Wing 19 100% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 4 BHK | 76 | 48 | 28 |
| 4 BHK | 76 | 48 | 28 |
| 4 BHK | 76 | 48 | 28 |
| 4 BHK | 76 | 48 | 28 |
| 4 BHK | 76 | 48 | 28 |
| 4 BHK | 76 | 48 | 28 |
| 4 BHK | 76 | 48 | 28 |
| 4 BHK | 76 | 48 | 28 |
| Parking | 76 | 60 | 16 |
Wing 14 100% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 1 BHK | 111 | 109 | 2 |
| 1 BHK | 111 | 109 | 2 |
| 1 BHK | 111 | 109 | 2 |
| 1 BHK | 111 | 109 | 2 |
| 1 BHK | 111 | 109 | 2 |
| 1 BHK | 111 | 109 | 2 |
| 1 BHK | 111 | 109 | 2 |
| 1 BHK | 111 | 109 | 2 |
| Parking | 56 | 56 | — |
Wing 15 100% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 1 BHK | 114 | 108 | 6 |
| 1 BHK | 114 | 108 | 6 |
| 1 BHK | 114 | 108 | 6 |
| 1 BHK | 114 | 108 | 6 |
| 1 BHK | 114 | 108 | 6 |
| 1 BHK | 114 | 108 | 6 |
| 1 BHK | 114 | 108 | 6 |
| 1 BHK | 114 | 108 | 6 |
| Parking | 57 | 54 | 3 |
Wing 16 100% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 3 BHK | 112 | 108 | 4 |
| 3 BHK | 112 | 108 | 4 |
| 3 BHK | 112 | 108 | 4 |
| 3 BHK | 112 | 108 | 4 |
| 3 BHK | 112 | 108 | 4 |
| 3 BHK | 112 | 108 | 4 |
| 3 BHK | 112 | 108 | 4 |
| 3 BHK | 112 | 108 | 4 |
| Parking | 112 | 108 | 4 |
Wing 17 100% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 3 BHK | 112 | 106 | 6 |
| 3 BHK | 112 | 106 | 6 |
| 3 BHK | 112 | 106 | 6 |
| 3 BHK | 112 | 106 | 6 |
| 3 BHK | 112 | 106 | 6 |
| 3 BHK | 112 | 106 | 6 |
| 3 BHK | 112 | 106 | 6 |
| 3 BHK | 112 | 106 | 6 |
| Parking | 112 | 107 | 5 |
Wing 18 100% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 4 BHK | 75 | 55 | 20 |
| 4 BHK | 75 | 55 | 20 |
| 4 BHK | 75 | 55 | 20 |
| 4 BHK | 75 | 55 | 20 |
| 4 BHK | 75 | 55 | 20 |
| 4 BHK | 75 | 55 | 20 |
| 4 BHK | 75 | 55 | 20 |
| 4 BHK | 75 | 55 | 20 |
| Parking | 75 | 65 | 10 |
Wing 19 100% complete
| Unit type | Total | Booked | Available |
|---|---|---|---|
| 4 BHK | 76 | 45 | 31 |
| 4 BHK | 76 | 45 | 31 |
| 4 BHK | 76 | 45 | 31 |
| 4 BHK | 76 | 45 | 31 |
| 4 BHK | 76 | 45 | 31 |
| 4 BHK | 76 | 45 | 31 |
| 4 BHK | 76 | 45 | 31 |
| 4 BHK | 76 | 45 | 31 |
| Parking | 76 | 52 | 24 |
Unit Specifications
| Unit type | Carpet area (sqft) | Units | |
|---|---|---|---|
| 1 BHK | 436 | 450 | Estimate ROI → |
| 3 BHK | 1,132–1,453 | 448 | Estimate ROI → |
| 4 BHK | 1,564–1,618 | 302 | Estimate ROI → |
Show escrow account details
- Bank
- KOTAK MAHINDRA BANK
- Branch
- MG road
- IFSC
- KKBK0008066
- 70% Collection A/C
- 2349105620
Project details
- Registration no.
- PRM/KA/RERA/1251/446/PR/200923/006269
- District
- Bengaluru Urban
- Taluk
- Bengaluru East
- Promoter
- SOBHA LIMITED
- Firm type
- Company
- PAN
- AABCS7723E
- GSTIN
- 29AABCS7723E1ZB
- Total units
- 604
- Project start
- 2023-10-01
- FAR sanctioned
- 2.99
- Total cost
- ₹701.28 Cr
- Land/property litigation
- No
- Proposed completion
- 2028-12-31
- Project address
- "PROPOSED RESIDENTIAL DEVELOPMENT PROJECT AT SY.NO.47/1B,47/2B, KYALASANAHALLI VILLAGE , WARD NO.25, MAHADEVAPURA ZONE, K.R. PURAM HOBLI, BANGALORE "
Buyer Risk Report 5 complaints
2 risk signals detected · 5 complaints on file from this project's K-RERA quarterly filings.
Sign in free — no password — to see exactly which quarters and complaints triggered these flags.
Sign in to see full details →A few details and our team will reach out — no referral fee, just a connection.
✓ We're on it — our team will reach out to you shortly.
Show documents on file with K-RERA (170)
| BESCOM (electricity) | on file |
| BWSSB (water & sewerage) | on file |
| Fire NOC | on file |
| KSPCB (pollution control) | on file |
| SEIAA (environmental clearance) | on file |
| Airport / Air Force NOC | not found |
| Telecom (BSNL) NOC | on file |
| Lift license | not found |
| Form-1 (project registration) | not found |
| Form-2/3 (CA certificate) | not found |
| Form-B / Sec 3(1) affidavit | on file |
| Certificate of incorporation | not found |
| GST certificate | on file |
| PAN card | on file |
| Partnership deed / firm registration | not found |
- Promoter financials
- 17 on file
- Legal / land documents
- 10 on file · 2 marked not available
- Other documents
- 52 on file · 13 marked not available
- Plan approvals
- 52 on file
- Sale/allotment documents
- 6 on file
- Technical certificates
- 2 on file
Frequently Asked Questions
Is Sobha Neopolis Phase 1 - W 14, 15, 16, 17, 18 &19 RERA registered in Karnataka?
Yes. Sobha Neopolis Phase 1 - W 14, 15, 16, 17, 18 &19 is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1251/446/PR/200923/006269.
What is the RERA registration number of Sobha Neopolis Phase 1 - W 14, 15, 16, 17, 18 &19?
The K-RERA registration number of Sobha Neopolis Phase 1 - W 14, 15, 16, 17, 18 &19 is PRM/KA/RERA/1251/446/PR/200923/006269.
What is the current construction status of Sobha Neopolis Phase 1 - W 14, 15, 16, 17, 18 &19?
As of Q2 2026-27, Sobha Neopolis Phase 1 - W 14, 15, 16, 17, 18 &19 is 64% complete according to its latest K-RERA quarterly filing.
Are flats still available in Sobha Neopolis Phase 1 - W 14, 15, 16, 17, 18 &19?
Yes. As per the latest K-RERA quarterly filing (Q2 2026-27), Sobha Neopolis Phase 1 - W 14, 15, 16, 17, 18 &19 has 30 unit(s) available for purchase.
How many flats have been sold in Sobha Neopolis Phase 1 - W 14, 15, 16, 17, 18 &19?
As per the latest K-RERA filing (Q2 2026-27), 570 out of 604 units in Sobha Neopolis Phase 1 - W 14, 15, 16, 17, 18 &19 have been sold or booked.
Are 1 BHK flats available in Sobha Neopolis Phase 1 - W 14, 15, 16, 17, 18 &19?
Yes. According to the latest K-RERA quarterly filing, there are 1 1 BHK unit(s) available in Sobha Neopolis Phase 1 - W 14, 15, 16, 17, 18 &19, Bengaluru Urban.
Are 3 BHK flats available in Sobha Neopolis Phase 1 - W 14, 15, 16, 17, 18 &19?
Yes. According to the latest K-RERA quarterly filing, there are 1 3 BHK unit(s) available in Sobha Neopolis Phase 1 - W 14, 15, 16, 17, 18 &19, Bengaluru Urban.
Are 4 BHK flats available in Sobha Neopolis Phase 1 - W 14, 15, 16, 17, 18 &19?
Yes. According to the latest K-RERA quarterly filing, there are 28 4 BHK unit(s) available in Sobha Neopolis Phase 1 - W 14, 15, 16, 17, 18 &19, Bengaluru Urban.
Are there any RERA complaints against Sobha Neopolis Phase 1 - W 14, 15, 16, 17, 18 &19?
Yes. Sobha Neopolis Phase 1 - W 14, 15, 16, 17, 18 &19 has 5 complaint(s) filed against it on the K-RERA portal. Review these on the official K-RERA website before making a purchase decision.
How many RERA complaints does SOBHA LIMITED have?
SOBHA LIMITED, the builder/promoter of Sobha Neopolis Phase 1 - W 14, 15, 16, 17, 18 &19, has 225 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.
Who is the builder or developer of Sobha Neopolis Phase 1 - W 14, 15, 16, 17, 18 &19?
Sobha Neopolis Phase 1 - W 14, 15, 16, 17, 18 &19 is developed by SOBHA LIMITED, a company registered with K-RERA in Bengaluru Urban, Karnataka.
When did Sobha Neopolis Phase 1 - W 14, 15, 16, 17, 18 &19 last file a quarterly update with K-RERA?
Sobha Neopolis Phase 1 - W 14, 15, 16, 17, 18 &19 last filed a quarterly update for Q2 2026-27 on 2026-10-14. The project has submitted 4 quarterly report(s) on K-RERA to date.