Projects / Sobha Neopolis Phase 4 - 3, 4, 8 & 9
+ Compare with another project

Sobha Neopolis Phase 4 - 3, 4, 8 & 9

Bengaluru Urban · SOBHA LIMITED PRM/KA/RERA/1251/446/PR/220923/006283
4 complaints · 37% built
Filed — · Q1 2026-27
Fund safety: no flags
Construction
37%
complete
Sold
306
of 376 total units
Available
68
units
3 BHK: 6
4 BHK: 130
Complaints
4
on project · 224 on builder
Construction progress
% complete per quarter
Sales velocity
Units sold per quarter · cumulative booked (line)
Inventory drain
Available units over time
Show financial data (advance collected vs withdrawn)
Quarterly financials
₹ Crore — advance collected vs amount withdrawn this quarter

Quarter-wise Tower Data

Filed: 2026-07-13 · Project 37% complete
Wing 3 0% complete
Unit type Total Booked Available
3 BHK 111 108 3
3 BHK 111 108 3
Parking 111 109 2
Floor completion
Floor 0
0.0%
Floor 0
0.0%
Floor 1
0.0%
Floor 1
0.0%
Floor 2
0.0%
Floor 2
0.0%
Floor 3
0.0%
Floor 3
0.0%
Floor 4
0.0%
Floor 4
0.0%
Floor 5
0.0%
Floor 5
0.0%
Floor 6
0.0%
Floor 6
0.0%
Floor 7
0.0%
Floor 7
0.0%
Floor 8
0.0%
Floor 8
0.0%
Floor 9
0.0%
Floor 9
0.0%
Floor 10
0.0%
Floor 10
0.0%
Floor 11
0.0%
Floor 11
0.0%
Floor 12
0.0%
Floor 12
0.0%
Floor 13
0.0%
Floor 13
0.0%
Floor 14
0.0%
Floor 14
0.0%
Floor 15
0.0%
Floor 15
0.0%
Floor 16
0.0%
Floor 16
0.0%
Floor 17
0.0%
Floor 17
0.0%
Floor 18
0.0%
Floor 18
0.0%
Wing 4 0% complete
Unit type Total Booked Available
4 BHK 76 40 36
4 BHK 76 40 36
Parking 76 76 —
Floor completion
Floor 0
0.0%
Floor 0
0.0%
Floor 1
0.0%
Floor 1
0.0%
Floor 2
0.0%
Floor 2
0.0%
Floor 3
0.0%
Floor 3
0.0%
Floor 4
0.0%
Floor 4
0.0%
Floor 5
0.0%
Floor 5
0.0%
Floor 6
0.0%
Floor 6
0.0%
Floor 7
0.0%
Floor 7
0.0%
Floor 8
0.0%
Floor 8
0.0%
Floor 9
0.0%
Floor 9
0.0%
Floor 10
0.0%
Floor 10
0.0%
Floor 11
0.0%
Floor 11
0.0%
Floor 12
0.0%
Floor 12
0.0%
Floor 13
0.0%
Floor 13
0.0%
Floor 14
0.0%
Floor 14
0.0%
Floor 15
0.0%
Floor 15
0.0%
Floor 16
0.0%
Floor 16
0.0%
Floor 17
0.0%
Floor 17
0.0%
Floor 18
0.0%
Floor 18
0.0%
Wing 8 100% complete
Unit type Total Booked Available
3 BHK 111 111 0
3 BHK 111 111 0
Parking 111 111 —
Floor completion
Floor 0
100.0%
Floor 0
100.0%
Floor 1
100.0%
Floor 1
100.0%
Floor 2
100.0%
Floor 2
100.0%
Floor 3
100.0%
Floor 3
100.0%
Floor 4
100.0%
Floor 4
100.0%
Floor 5
100.0%
Floor 5
100.0%
Floor 6
100.0%
Floor 6
100.0%
Floor 7
100.0%
Floor 7
100.0%
Floor 8
100.0%
Floor 8
100.0%
Floor 9
100.0%
Floor 9
100.0%
Floor 10
100.0%
Floor 10
100.0%
Floor 11
100.0%
Floor 11
100.0%
Floor 12
100.0%
Floor 12
100.0%
Floor 13
100.0%
Floor 13
100.0%
Floor 14
100.0%
Floor 14
100.0%
Floor 15
100.0%
Floor 15
100.0%
Floor 16
100.0%
Floor 16
100.0%
Floor 17
100.0%
Floor 17
100.0%
Floor 18
100.0%
Floor 18
100.0%
Wing 9 89% complete
Unit type Total Booked Available
4 BHK 76 47 29
4 BHK 76 47 29
Parking 76 70 6
Floor completion
Floor 0
100.0%
Floor 0
100.0%
Floor 1
100.0%
Floor 1
100.0%
Floor 2
100.0%
Floor 2
100.0%
Floor 3
100.0%
Floor 3
100.0%
Floor 4
100.0%
Floor 4
100.0%
Floor 5
100.0%
Floor 5
100.0%
Floor 6
100.0%
Floor 6
100.0%
Floor 7
100.0%
Floor 7
100.0%
Floor 8
100.0%
Floor 8
100.0%
Floor 9
100.0%
Floor 9
100.0%
Floor 10
100.0%
Floor 10
100.0%
Floor 11
100.0%
Floor 11
100.0%
Floor 12
100.0%
Floor 12
100.0%
Floor 13
100.0%
Floor 13
100.0%
Floor 14
100.0%
Floor 14
100.0%
Floor 15
100.0%
Floor 15
100.0%
Floor 16
100.0%
Floor 16
100.0%
Floor 17
0.0%
Floor 17
0.0%
Floor 18
0.0%
Floor 18
0.0%

Unit Specifications

Unit type Carpet area (sqft) Units
3 BHK 1,132–1,453 444 Estimate ROI →
4 BHK 1,564–1,618 304 Estimate ROI →
Show escrow account details
Escrow Accounts
Bank
KOTAK MAHINDRA BANK
Branch
MG road
IFSC
KKBK0008066
70% Collection A/C
2349105606

Project details

Registration no.
PRM/KA/RERA/1251/446/PR/220923/006283
District
Bengaluru Urban
Taluk
Anekal
Promoter
SOBHA LIMITED
Firm type
Company
PAN
AABCS7723E
GSTIN
29AABCS7723E1ZB
Total units
376
Project start
2024-04-01
FAR sanctioned
2.99
Total cost
₹589.50 Cr
Land/property litigation
No
Proposed completion
2031-12-31
Project address
Sy No. 107(P), 115/2, 115/3, 115/4, 115/5, 116/3 situated at Nagondanahalli village and Sy No. 30/1, 30/6, Situated at Hagadur Village, K.R.Puram Hobli

Buyer Risk Report 4 complaints

1 risk signal detected · 4 complaints on file from this project's K-RERA quarterly filings.

Sign in free — no password — to see exactly which quarters and complaints triggered these flags.

Sign in to see full details →
Show documents on file with K-RERA (170)
Documents on file
Government NOCs
BESCOM (electricity) on file
BWSSB (water & sewerage) on file
Fire NOC on file
KSPCB (pollution control) on file
SEIAA (environmental clearance) on file
Airport / Air Force NOC not found
Telecom (BSNL) NOC on file
Lift license not found
RERA statutory forms
Form-1 (project registration) not found
Form-2/3 (CA certificate) not found
Form-B / Sec 3(1) affidavit on file
Company KYC
Certificate of incorporation not found
GST certificate on file
PAN card on file
Partnership deed / firm registration not found
Promoter financials
17 on file
Legal / land documents
9 on file · 2 marked not available
Other documents
52 on file · 13 marked not available
Plan approvals
52 on file · 1 marked not available
Sale/allotment documents
6 on file
Technical certificates
2 on file
Inventory of documents the promoter has uploaded to their K-RERA project page — not a review of their contents. "Not found" means no filed document matched that item by name; it doesn't necessarily apply to every project (e.g. an airport-proximity NOC).

Frequently Asked Questions

Based on K-RERA registered data for Sobha Neopolis Phase 4 - 3, 4, 8 & 9
Is Sobha Neopolis Phase 4 - 3, 4, 8 & 9 RERA registered in Karnataka?

Yes. Sobha Neopolis Phase 4 - 3, 4, 8 & 9 is registered with the Karnataka Real Estate Regulatory Authority (K-RERA) under registration number PRM/KA/RERA/1251/446/PR/220923/006283.

What is the RERA registration number of Sobha Neopolis Phase 4 - 3, 4, 8 & 9?

The K-RERA registration number of Sobha Neopolis Phase 4 - 3, 4, 8 & 9 is PRM/KA/RERA/1251/446/PR/220923/006283.

What is the current construction status of Sobha Neopolis Phase 4 - 3, 4, 8 & 9?

As of Q1 2026-27, Sobha Neopolis Phase 4 - 3, 4, 8 & 9 is 37% complete according to its latest K-RERA quarterly filing.

Are flats still available in Sobha Neopolis Phase 4 - 3, 4, 8 & 9?

Yes. As per the latest K-RERA quarterly filing (Q1 2026-27), Sobha Neopolis Phase 4 - 3, 4, 8 & 9 has 68 unit(s) available for purchase.

How many flats have been sold in Sobha Neopolis Phase 4 - 3, 4, 8 & 9?

As per the latest K-RERA filing (Q1 2026-27), 306 out of 376 units in Sobha Neopolis Phase 4 - 3, 4, 8 & 9 have been sold or booked.

Are 3 BHK flats available in Sobha Neopolis Phase 4 - 3, 4, 8 & 9?

Yes. According to the latest K-RERA quarterly filing, there are 6 3 BHK unit(s) available in Sobha Neopolis Phase 4 - 3, 4, 8 & 9, Bengaluru Urban.

Are 4 BHK flats available in Sobha Neopolis Phase 4 - 3, 4, 8 & 9?

Yes. According to the latest K-RERA quarterly filing, there are 130 4 BHK unit(s) available in Sobha Neopolis Phase 4 - 3, 4, 8 & 9, Bengaluru Urban.

Are there any RERA complaints against Sobha Neopolis Phase 4 - 3, 4, 8 & 9?

Yes. Sobha Neopolis Phase 4 - 3, 4, 8 & 9 has 4 complaint(s) filed against it on the K-RERA portal. Review these on the official K-RERA website before making a purchase decision.

How many RERA complaints does SOBHA LIMITED have?

SOBHA LIMITED, the builder/promoter of Sobha Neopolis Phase 4 - 3, 4, 8 & 9, has 224 complaint(s) filed against them across all their K-RERA registered projects in Karnataka.

Who is the builder or developer of Sobha Neopolis Phase 4 - 3, 4, 8 & 9?

Sobha Neopolis Phase 4 - 3, 4, 8 & 9 is developed by SOBHA LIMITED, a company registered with K-RERA in Bengaluru Urban, Karnataka.

When did Sobha Neopolis Phase 4 - 3, 4, 8 & 9 last file a quarterly update with K-RERA?

Sobha Neopolis Phase 4 - 3, 4, 8 & 9 last filed a quarterly update for Q1 2026-27 on 2026-07-13. The project has submitted 3 quarterly report(s) on K-RERA to date.